News Flash

Posted on: June 11, 2021

Project Update | June 11

American Tobacco Waterline Replacement

American Tobacco District Waterline Replacement – Phase 1 Project Update and Two-Week Look Ahead

June 11, 2021

The City appreciates your ongoing patience with the work along the busy corridors associated with this project.  Additional inf...

Read on...

American Tobacco District Waterline Replacement Project Updates
Posted on: June 4, 2021

Project Update | June 4

American Tobacco Waterline Replacement

American Tobacco District Waterline Replacement – Phase 1 Project Update and Two-Week Look Ahead

June 4, 2021

The City appreciates your ongoing patience with the work along the busy corridors associated with this project.  Additional info...

Read on...

American Tobacco District Waterline Replacement Project Updates
Posted on: May 28, 2021

Project Update | May 28

American Tobacco Waterline Replacement

American Tobacco District Waterline Replacement – Phase 1 Project Update and Two-Week Look Ahead

May 28, 2021

The City appreciates your ongoing patience with the work along the busy corridors associated with this project.  Additional info...

Read on...

American Tobacco District Waterline Replacement Project Updates
Posted on: May 21, 2021

Project Update | May 21

American Tobacco Waterline Replacement

American Tobacco District Waterline Replacement – Phase 1 Project Update and Two-Week Look Ahead

May 21, 2021

The City appreciates your ongoing patience with the work along the busy corridors associated with this project.  Additional info...

Read on...

American Tobacco District Waterline Replacement Project Updates
Posted on: May 14, 2021

Project Update | May 14

American Tobacco Waterline Replacement

American Tobacco District Waterline Replacement – Phase 1 Project Update and Two-Week Look Ahead

May 14, 2021

The City appreciates your ongoing patience with the work along the busy corridors associated with this project.  Additional info...

Read on...

American Tobacco District Waterline Replacement Project Updates
Posted on: May 7, 2021

Project Update | May 7

American Tobacco Waterline Replacement

American Tobacco District Waterline Replacement – Phase 1 Project Update and Two-Week Look Ahead

May 7, 2021

The City appreciates your ongoing patience with the work along the busy corridors associated with this project.  Additional infor...

Read on...

American Tobacco District Waterline Replacement Project Updates
Posted on: April 30, 2021

Project Update | April 30

American Tobacco District Waterline Replacement – Phase 1 Project Update and Two-Week Look Ahead

April 30, 2021

The City appreciates your ongoing patience with the work along the busy corridors associated with this project.  Additional in...

Read on...

American Tobacco District Waterline Replacement Project Updates
Posted on: April 23, 2021

Project Update | April 23

American Tobacco Waterline Replacement

American Tobacco District Waterline Replacement – Phase 1 Project Update and Two-Week Look Ahead

April 23, 2021

The City appreciates your ongoing patience with the work along the busy corridors associated with this project.  Additional information ...

Read on...

American Tobacco District Waterline Replacement Project Updates
Posted on: April 16, 2021

Project Update | April 16

American Tobacco Waterline Replacement

American Tobacco District Waterline Replacement – Phase 1 Project Update and Two-Week Look Ahead

April 16, 2021

The City appreciates your ongoing patience with the work along the busy corridors associated with this project.  Additional in...

Read on...

American Tobacco District Waterline Replacement Project Updates
Posted on: April 9, 2021

Project Update | April 9

American Tobacco Waterline Replacement

American Tobacco District Waterline Replacement – Phase 1 Project Update and Two-Week Look Ahead

April 9, 2021

The City appreciates your ongoing patience with the work along the busy corridors associated with this project.  Additional inf...

Read on...

American Tobacco District Waterline Replacement Project Updates
Posted on: April 2, 2021

Project Update | April 2

American Tobacco Waterline Replacement

American Tobacco District Waterline Replacement – Phase 1 Project Update and Two-Week Look Ahead

April 2, 2021

The City appreciates your ongoing patience with the work along the busy corridors associated with this project.  Additional inf...

Read on...

American Tobacco District Waterline Replacement Project Updates
Posted on: March 26, 2021

Project Update | March 26

American Tobacco Waterline Replacement

American Tobacco District Waterline Replacement – Phase 1 Project Update and Two-Week Look Ahead

March 26, 2021

The City appreciates your ongoing patience with the work along the busy corridors associated with this project.  Additional in...

Read on...

American Tobacco District Waterline Replacement Project Updates
Posted on: March 19, 2021

Project Update | March 19

American Tobacco Waterline Replacement

American Tobacco District Waterline Replacement – Phase 1 Project Update and Two-Week Look Ahead

 

March 19, 2021

 

The City appreciates your ongoing patience with the work along the busy corridors associated with this project.  Add...

Read on...

American Tobacco District Waterline Replacement Project Updates
Posted on: March 12, 2021

Project Update | March 12

American Tobacco Waterline Replacement

American Tobacco District Waterline Replacement – Phase 1 Project Update and Two-Week Look Ahead

March 12, 2021

The City appreciates your ongoing patience with the work along the busy corridors associated with this project.  Additional in...

Read on...

American Tobacco District Waterline Replacement Project Updates
Posted on: March 5, 2021

Project Update | March 5

American Tobacco Waterline Replacement

American Tobacco District Waterline Replacement – Phase 1 Project Update and Two-Week Look Ahead

 

March 5, 2021

 

The City appreciates your ongoing patience with the work along the busy corridors associated with this project. &...

Read on...

American Tobacco District Waterline Replacement Project Updates
Posted on: February 26, 2021

Project Update | February 26

American Tobacco Waterline Replacement

American Tobacco District Waterline Replacement – Phase 1 Project Update and Two-Week Look Ahead

February 26, 2021

The City appreciates your ongoing patience with the work along the busy corridors associated with this project.  Additional...

Read on...

American Tobacco District Waterline Replacement Project Updates
Posted on: February 19, 2021

Project Update | February 19

American Tobacco Waterline Replacement

American Tobacco District Waterline Replacement – Phase 1 Project Update and Two-Week Look Ahead

 February 19, 2021

The City appreciates your ongoing patience with the work along the busy corridors associated with this project.  ...

Read on...

American Tobacco District Waterline Replacement Project Updates
Posted on: February 12, 2021

Project Update | February 12

American Tobacco Waterline Replacement

American Tobacco District Waterline Replacement – Phase 1 Project Update and Two-Week Look Ahead

 

February 12, 2021

 

The City appreciates your ongoing patience with the work along the busy corridors associated with this project. ...

Read on...

American Tobacco District Waterline Replacement Project Updates
Posted on: February 5, 2021

Project Update | February 5

American Tobacco District Waterline Replacement – Phase 1 Project Update and Two-Week Look Ahead

 

February 5, 2021

 

The City appreciates your ongoing patience with the work along the busy corridors associated with this project. &...

Read on...

American Tobacco District Waterline Replacement Project Updates
Posted on: January 29, 2021

Project Update | January 29

American Tobacco Waterline Replacement

American Tobacco District Waterline Replacement – Phase 1 Project Update and Two-Week Look Ahead

January 29, 2021

The City appreciates your ongoing patience with the work along the busy corridors associated with this project.  Additional ...

Read on...

American Tobacco District Waterline Replacement Project Updates
Posted on: January 22, 2021

Project Update | January 22

American Tobacco Waterline Replacement

American Tobacco District Waterline Replacement – Phase 1 Project Update and Two-Week Look Ahead

January 22, 2021

The City appreciates your ongoing patience with the work along the busy corridors associated with this project.  Additional ...

Read on...

American Tobacco District Waterline Replacement Project Updates
Posted on: January 15, 2021

Project Update | January 15

American Tobacco District Waterline Replacement – Phase 1 Project Update and Two-Week Look Ahead

January 15, 2021

The City appreciates your ongoing patience with the work along the busy corridors associated with this project.  Additional informatio...

Read on...

American Tobacco District Waterline Replacement Project Updates
Posted on: January 8, 2021

Project Update | January 8

American Tobacco District Waterline Replacement – Phase 1 Project Update and Two-Week Look Ahead

January 8, 2021

The City appreciates your ongoing patience with the work along the busy corridors associated with this project.  Additional i...

Read on...

American Tobacco District Waterline Replacement Project Updates
Posted on: December 31, 2020

Project Update | December 31

American Tobacco District Waterline Replacement – Phase 1 Project Update and Two-Week Look Ahead

 December 31, 2020

The City appreciates your ongoing patience with the work along the busy corridors associated with this project.  Additional...

Read on...

American Tobacco District Waterline Replacement Project Updates
Posted on: December 24, 2020

Project Update | December 24

American Tobacco District Waterline Replacement – Phase 1 Project Update and Two-Week Look Ahead

 December 24, 2020

The City appreciates your ongoing patience with the work along the busy corridors associated with this project.  ...

Read on...

American Tobacco District Waterline Replacement Project Updates
Posted on: December 18, 2020

Project Update | December 18

American Tobacco District Waterline Replacement – Phase 1 Project Update and Two-Week Look Ahead

 December 18, 2020

 The City appreciates your ongoing patience with the work along the busy corridors associated with this project.  ...

Read on...

American Tobacco District Waterline Replacement Project Updates
Posted on: December 11, 2020

Project Update | December 11

American Tobacco District Waterline Replacement – Phase 1 Project Update and Two-Week Look Ahead

 December 11, 2020

 The City appreciates your ongoing patience with the work along the busy corridors associated with this project. ...

Read on...

American Tobacco District Waterline Replacement Project Updates
Posted on: December 4, 2020

Project Update | December 4

American Tobacco District Waterline Replacement – Phase 1 Project Update and Two-Week Look Ahead

December 4, 2020

The City appreciates your ongoing patience with the work along the busy corridors associated with this project.  Additional ...

Read on...

American Tobacco District Waterline Replacement Project Updates
Posted on: November 20, 2020

November 20 | Project Update

American Tobacco District Waterline Replacement – Phase 1 Project Update and Two-Week Look Ahead

November 20, 2020

The City appreciates your ongoing patience with the work along the busy corridors associated with this project.  Additional...

Read on...

American Tobacco District Waterline Replacement Project Updates
Posted on: November 13, 2020

November 13 | Project Update

This look ahead includes westbound closures of Jackson and Yancey Streets. Thank you for your patience and your continued interest in this project.

Additional information can be found at: https://durhamnc.gov/2780/American-Tobacco-District-Waterline-Repl.

&...

Read on...

American Tobacco District Waterline Replacement Project Updates
Posted on: November 6, 2020

November 6 | Project Update

Here's your two-week look ahead for this Friday! The City appreciates your ongoing patience with the work along the busy corridors associated with this project.  Visit our project page for additional information.

 Planned Road / ...

Read on...

American Tobacco District Waterline Replacement Project Updates
Posted on: October 29, 2020

October 30 | Project Update

Thank you again for your interest in the American Tobacco District Waterline Replacement Project. Here's what you can expect from construction in the first weeks of November. Please note, the northbound lane closure of Willard Street currently in place wi...

Read on...

American Tobacco District Waterline Replacement Project Updates
Posted on: October 23, 2020

October 23 | Project Update

Here's your two-week look ahead at the American Tobacco District Waterline Replacement Project. We appreciate your support and thank you for your patience as work moves along.  Additional information can be found at: https://durhamnc.gov...

Read on...

American Tobacco District Waterline Replacement Project Updates
Posted on: October 16, 2020

Project Update | October 16, 2020

Thank you for keeping up with progress through these two-week look ahead reports! Phase 1 of construction began on October 5, 2020. The City appreciates your ongoing patience with the work along the busy corridors associated with this project.  

P...

Read on...

American Tobacco District Waterline Replacement Project Updates
Posted on: October 8, 2020

Project Update | October 9, 2020

Construction of the American Tobacco District Waterline Replacement – Phase 1 began on October 5, 2020. As always, we appreciate your patience with any associated inconveniences or delays.

Planned Road / Lane Closures will occur as follows:

  • Week o...
Read on...

American Tobacco District Waterline Replacement Project Updates
Posted on: October 2, 2020

Project Update | October 2, 2020

Construction is scheduled to begin on Monday! Here's the rundown of what to expect throughout the first two weeks of this project. We appreciate your ongoing patience with the work along these busy corridors.  

Planned Road / Lane Closure...

Read on...

American Tobacco District Waterline Replacement Project Updates
Posted on: September 25, 2020

Phase 1 Project to Begin October 5, 2020

Construction of the American Tobacco District Waterline Replacement – Phase 1 project is planned to begin on October 5, 2020. Additional information on this project can be found at: https://durhamnc.gov/2780/American-Tobacco-District-Waterline-Repl. The C...

Read on...

American Tobacco District Waterline Replacement Project Updates
Posted on: July 30, 2020

We'd like to help you stay updated on this important project!

We’re replacing existing 1930s era water mains near and within the American Tobacco District to improve service delivery. Approximately 10,000 feet of waterlines within the American Tobacco vicinity area will be replaced, and approximately 4,600...

Read on...

American Tobacco District Waterline Replacement Project Updates