American Tobacco District Waterline Replacement – Phase 1 Project Update and Two-Week Look Ahead

August 27, 2021

The City appreciates your ongoing patience with the work along the busy corridors associated with this project. Additional information regarding this project can be found at: https://durhamnc.gov/2780/American-Tobacco-District-Waterline-Repl.

Planned Road / Lane Closures will occur as follows:

  • Week of 8/30: 
    • Lane closures and shifts in Chapel Hill Street between Gregson Street and Pettigrew Street.
    • Lane closures and shifts in Duke Street between Yancey Street and Pettigrew Street.
    • Lane closures and shifts in Gregson Street between Pettigrew Street and Chapel Hill Street.
  • Week of 9/7: 
    • Lane closures and shifts in Chapel Hill Street between Gregson Street and Pettigrew Street.
    • Lane closures and shifts in Duke Street between Yancey Street and Pettigrew Street.
    • Lane closures and shifts in Gregson Street between Pettigrew Street and Chapel Hill Street.

Bicycle Lane and Sidewalk impacts will occur as follows:

  • Dedicated bike lanes in Chapel Hill Street between Gregson and Pettigrew streets will be removed as part of roadway lane shifts.
  • Varying sidewalk on the north and south sides of Chapel Hill Street between Gregson and Pettigrew streets will be closed to accommodate waterline installation.
  • The sidewalk on the west side of Duke Street between Yancey Street and Pettigrew Street will have temporary closures to accommodate waterline installation.

Saturday – Sunday August 28-29, 2021:

  • No work will take place on Saturday or Sunday.

Week of August 30, 2021:

  • Duke Street between Yancey Street / NC-147 and Pettigrew Street will have lane closures and traffic shifts to accommodate waterline installation.
    • Lane shifts in Duke Street between Yancey and Pettigrew streets using temporary pavement markings will be implemented.
    • Lane shifts with flaggers or temporary detours will be utilized for traffic control while work is taking place near the Duke / Chapel Hill and Duke / Memorial intersections and at waterline connection locations.
    • Traffic control signs and markings will be used for the lane closures and shifts.
    • The sidewalk on the west side of Duke Street between Yancey Street and Pettigrew Street will have temporary closures to accommodate waterline installation.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Planned work hours are 7 AM to 7 PM.
    • No water or sewer service disruptions are anticipated.
  • Chapel Hill Street between Gregson Street and Willard Street will have lane closures and traffic shifts to accommodate waterline installation.
    • Lane shifts in Chapel Hill Street between Gregson and Pettigrew streets using temporary pavement markings are implemented.
    • Lane shifts with flaggers will be utilized for traffic control while work is taking place in intersections and at waterline connection locations.
    • Traffic control signs and markings will be used for the lane closures and shifts.
    • The sidewalk on the north side of Chapel Hill Street between Willard and Gregson streets will be closed to accommodate waterline installation.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Planned work hours are 7 AM to 7 PM.
    • No water or sewer service disruptions are anticipated.
  • Gregson Street between Pettigrew Street and Chapel Hill Street will have lane closures while work is taking place near the Chapel Hill Street / Gregson Street intersection.
    • Lane shifts in Gregson Street between Pettigrew and Chapel Hill streets will be implemented between 9 AM and 4 PM.
    • Traffic control signs and markings will be used for the lane closures and shifts.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Planned work hours in Gregson Street are 9 AM to 4 PM.
    • No water or sewer service disruptions are anticipated.

Saturday – Monday September 4-6, 2021:

  • No work will take place on Saturday, Sunday, or Monday (Labor Day).

Week of September 7, 2021:

  • Duke Street between Yancey Street / NC-147 and Pettigrew Street will have lane closures and traffic shifts to accommodate waterline installation.
    • Lane shifts in Duke Street between Yancey and Pettigrew streets using temporary pavement markings will be implemented.
    • Lane shifts with flaggers or temporary detours will be utilized for traffic control while work is taking place near the Duke / Chapel Hill and Duke / Memorial intersections and at waterline connection locations.
    • Traffic control signs and markings will be used for the lane closures and shifts.
    • The sidewalk on the west side of Duke Street between Yancey Street and Pettigrew Street will have temporary closures to accommodate waterline installation.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Planned work hours are 7 AM to 7 PM.
    • No water or sewer service disruptions are anticipated.
  • Chapel Hill Street between Gregson Street and Willard Street will have lane closures and traffic shifts to accommodate waterline installation.
    • Lane shifts in Chapel Hill Street between Gregson and Pettigrew streets using temporary pavement markings are implemented.
    • Lane shifts with flaggers will be utilized for traffic control while work is taking place in intersections and at waterline connection locations.
    • Traffic control signs and markings will be used for the lane closures and shifts.
    • The sidewalk on the north side of Chapel Hill Street between Willard and Gregson streets will be closed to accommodate waterline installation.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Planned work hours are 7 AM to 7 PM.
    • No water or sewer service disruptions are anticipated.
  • Gregson Street between Pettigrew Street and Chapel Hill Street will have lane closures while work is taking place near the Chapel Hill Street / Gregson Street intersection.
    • Lane shifts in Gregson Street between Pettigrew and Chapel Hill streets will be implemented between 9 AM and 4 PM.
    • Traffic control signs and markings will be used for the lane closures and shifts.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Planned work hours in Gregson Street are 9 AM to 4 PM.
    • No water or sewer service disruptions are anticipated.

Saturday – Sunday September 11-12, 2021:

  • No work will take place on Saturday or Sunday.

If you have questions, please email Lisa.Mitchell@durhamnc.gov.

Facebook Twitter Email

Other News in American Tobacco District Waterline Replacement Project Updates

American Tobacco Waterline Replacement

Project Update | October 15

Posted on: October 15, 2021
American Tobacco Waterline Replacement

Project Update | October 8

Posted on: October 8, 2021
American Tobacco Waterline Replacement

Project Update | October 1

Posted on: October 1, 2021
American Tobacco Waterline Replacement

Project Update | September 24

Posted on: September 24, 2021
American Tobacco Waterline Replacement

Project Update | September 17

Posted on: September 17, 2021
American Tobacco Waterline Replacement

Project Update | September 10

Posted on: September 10, 2021
American Tobacco Waterline Replacement

Project Update | September 3

Posted on: September 3, 2021
American Tobacco Waterline Replacement

Project Update | August 20

Posted on: August 20, 2021
American Tobacco Waterline Replacement

Project Update | August 13

Posted on: August 13, 2021
American Tobacco Waterline Replacement

Project Update | August 6

Posted on: August 6, 2021

Project Update | July 30

Posted on: July 30, 2021
American Tobacco Waterline Replacement

Project Update | July 23

Posted on: July 23, 2021
American Tobacco Waterline Replacement

Project Update | July 16

Posted on: July 16, 2021
American Tobacco Waterline Replacement

Project Update | July 9

Posted on: July 9, 2021
American Tobacco Waterline Replacement

Project Update | July 2

Posted on: July 2, 2021
American Tobacco Waterline Replacement

Project Update | June 25

Posted on: June 25, 2021
American Tobacco Waterline Replacement

Project Update | June 18

Posted on: June 18, 2021
American Tobacco Waterline Replacement

Project Update | June 11

Posted on: June 11, 2021
American Tobacco Waterline Replacement

Project Update | June 4

Posted on: June 4, 2021
American Tobacco Waterline Replacement

Project Update | May 28

Posted on: May 28, 2021
American Tobacco Waterline Replacement

Project Update | May 21

Posted on: May 21, 2021
American Tobacco Waterline Replacement

Project Update | May 14

Posted on: May 14, 2021
American Tobacco Waterline Replacement

Project Update | May 7

Posted on: May 7, 2021

Project Update | April 30

Posted on: April 30, 2021
American Tobacco Waterline Replacement

Project Update | April 23

Posted on: April 23, 2021
American Tobacco Waterline Replacement

Project Update | April 16

Posted on: April 16, 2021
American Tobacco Waterline Replacement

Project Update | April 9

Posted on: April 9, 2021
American Tobacco Waterline Replacement

Project Update | April 2

Posted on: April 2, 2021
American Tobacco Waterline Replacement

Project Update | March 26

Posted on: March 26, 2021
American Tobacco Waterline Replacement

Project Update | March 19

Posted on: March 19, 2021
American Tobacco Waterline Replacement

Project Update | March 12

Posted on: March 12, 2021
American Tobacco Waterline Replacement

Project Update | March 5

Posted on: March 5, 2021
American Tobacco Waterline Replacement

Project Update | February 26

Posted on: February 26, 2021
American Tobacco Waterline Replacement

Project Update | February 19

Posted on: February 19, 2021
American Tobacco Waterline Replacement

Project Update | February 12

Posted on: February 12, 2021

Project Update | February 5

Posted on: February 5, 2021
American Tobacco Waterline Replacement

Project Update | January 29

Posted on: January 29, 2021
American Tobacco Waterline Replacement

Project Update | January 22

Posted on: January 22, 2021

Project Update | January 15

Posted on: January 15, 2021

Project Update | January 8

Posted on: January 8, 2021

Project Update | December 31

Posted on: December 31, 2020

Project Update | December 24

Posted on: December 24, 2020

Project Update | December 18

Posted on: December 18, 2020

Project Update | December 11

Posted on: December 11, 2020

Project Update | December 4

Posted on: December 4, 2020

November 20 | Project Update

Posted on: November 20, 2020

November 13 | Project Update

Posted on: November 13, 2020

November 6 | Project Update

Posted on: November 6, 2020

October 30 | Project Update

Posted on: October 29, 2020

October 23 | Project Update

Posted on: October 23, 2020