American Tobacco District Waterline Replacement – Phase 1 Project Update and Two-Week Look Ahead

April 16, 2021

The City appreciates your ongoing patience with the work along the busy corridors associated with this project.  Additional information regarding this project can be found at: https://durhamnc.gov/2780/American-Tobacco-District-Waterline-Repl.

Planned Road / Lane Closures will occur as follows:

  • Week of 4/19: 
    • Full closure of Willard Street between Julian Carr and Jackson Street. 
    • Eastbound lane closure of Jackson Street east of Willard Street. 
  • Week of 4/26: 
    • Full closure of Willard Street between Julian Carr and Jackson Street. 
    • Eastbound lane closure of Jackson Street east of Willard Street. 
    • Full closure of Jackson Street between Duke Street and Willard Street.

Saturday – Sunday April 17-18, 2021:

  • No work will take place on Saturday or Sunday.

Week of April 19, 2021:

  • Willard Street between Julian Carr and Jackson Street will have a road closure to accommodate transmission main installation.
    • Traffic control signs and markings will be used for the Willard Street detour. 
    • Access to the ATC South Deck via Willard Street will remain open.
    • Sidewalk traffic will be disrupted.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Planned work hours are 7 AM to 7 PM.
    • No water or sewer service disruptions are anticipated.
  • Jackson Street east of Willard Street will have an eastbound lane closure to accommodate waterline installation.  
    • Traffic control signs and markings will be used for the Jackson Street detour.  
    • Access to the ATC North Deck via Willard / Julian Carr will be open during lane closure. 
    • Sidewalk traffic will be disrupted.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Planned work hours are 7 AM to 7 PM.
    • No water or sewer service disruptions are anticipated.

Saturday – Sunday April 24-25, 2021:

  • No work will take place on Saturday or Sunday.

Week of April 26, 2021:

  • Willard Street between Julian Carr and Jackson Street will have a road closure to accommodate transmission main installation.
    • Traffic control signs and markings will be used for the Willard Street detour. 
    • Access to the ATC South Deck via Willard Street will remain open.
    • Sidewalk traffic will be disrupted.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Planned work hours are 7 AM to 7 PM.
    • No water or sewer service disruptions are anticipated.
  • Jackson Street east of Willard Street will have an eastbound lane closure to accommodate waterline installation.  
    • Traffic control signs and markings will be used for the Jackson Street detour.  
    • Access to the ATC North Deck via Willard / Julian Carr will be open during lane closure. 
    • Sidewalk traffic will be disrupted.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Planned work hours are 7 AM to 7 PM.
    • No water or sewer service disruptions are anticipated.
  • Jackson Street between Duke Street and Willard Street will have a full closure to accommodate transmission main installation.  
    • Traffic control signs and markings will be used for the Jackson Street detour.  
    • Access to the parking deck and surface parking lot will be maintained.
    • Sidewalk traffic will be disrupted.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Planned work hours are 7 AM to 7 PM.
    • No water or sewer service disruptions are anticipated.

Saturday – Sunday May 1-2, 2021:

  • No work will take place on Saturday or Sunday.

If you have questions, please email Lisa.Mitchell@durhamnc.gov.

Facebook Twitter Email

Other News in American Tobacco District Waterline Replacement Project Updates

American Tobacco Waterline Replacement

Project Update | May 14

Posted on: May 14, 2021
American Tobacco Waterline Replacement

Project Update | May 7

Posted on: May 7, 2021

Project Update | April 30

Posted on: April 30, 2021
American Tobacco Waterline Replacement

Project Update | April 23

Posted on: April 23, 2021
American Tobacco Waterline Replacement

Project Update | April 9

Posted on: April 9, 2021
American Tobacco Waterline Replacement

Project Update | April 2

Posted on: April 2, 2021
American Tobacco Waterline Replacement

Project Update | March 26

Posted on: March 26, 2021
American Tobacco Waterline Replacement

Project Update | March 19

Posted on: March 19, 2021
American Tobacco Waterline Replacement

Project Update | March 12

Posted on: March 12, 2021
American Tobacco Waterline Replacement

Project Update | March 5

Posted on: March 5, 2021
American Tobacco Waterline Replacement

Project Update | February 26

Posted on: February 26, 2021
American Tobacco Waterline Replacement

Project Update | February 19

Posted on: February 19, 2021
American Tobacco Waterline Replacement

Project Update | February 12

Posted on: February 12, 2021

Project Update | February 5

Posted on: February 5, 2021
American Tobacco Waterline Replacement

Project Update | January 29

Posted on: January 29, 2021
American Tobacco Waterline Replacement

Project Update | January 22

Posted on: January 22, 2021

Project Update | January 15

Posted on: January 15, 2021

Project Update | January 8

Posted on: January 8, 2021

Project Update | December 31

Posted on: December 31, 2020

Project Update | December 24

Posted on: December 24, 2020

Project Update | December 18

Posted on: December 18, 2020

Project Update | December 11

Posted on: December 11, 2020

Project Update | December 4

Posted on: December 4, 2020

November 20 | Project Update

Posted on: November 20, 2020

November 13 | Project Update

Posted on: November 13, 2020

November 6 | Project Update

Posted on: November 6, 2020

October 30 | Project Update

Posted on: October 29, 2020

October 23 | Project Update

Posted on: October 23, 2020

Project Update | October 16, 2020

Posted on: October 16, 2020

Project Update | October 9, 2020

Posted on: October 8, 2020

Project Update | October 2, 2020

Posted on: October 2, 2020

Phase 1 Project to Begin October 5, 2020

Posted on: September 25, 2020