American Tobacco District Waterline Replacement Project Updates

Posted on: January 15, 2021

[ARCHIVED] Project Update | January 15

American Tobacco District Waterline Replacement – Phase 1 Project Update and Two-Week Look Ahead

January 15, 2021

The City appreciates your ongoing patience with the work along the busy corridors associated with this project.  Additional information regarding this project can be found at: https://durhamnc.gov/2780/American-Tobacco-District-Waterline-Repl.

Planned Road / Lane Closures will occur as follows:

  • Week of 1/18: 
    • Full closure of Willard Street between Blackwell Street and Julian Carr Street. 
    • Westbound lane closure of Jackson Street between Willard Street and Duke Street. 
  • Week of 1/25: 
    • Full closure of Willard Street between Blackwell Street and Julian Carr Street. 
    • Westbound lane closure of Jackson Street between Willard Street and Duke Street.
    • Lane closure in Duke Street between Morehead Ave and Jackson Street.

Week of January 18, 2021:

  • Willard Street between Blackwell Street and Yancey Street will have a road closure to accommodate sanitary sewer installation.
    • Traffic control signs and markings will be used for the Willard Street detour. 
    • Access to the ATC South Deck via Willard Street will be temporarily closed to accommodate installations.  Detour signs directing traffic to access the deck via Julian Carr will be used.
    • Sidewalk traffic will be disrupted.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Planned work hours are 7 AM to 7 PM.
    • No water or sewer service disruptions are anticipated.
  • Jackson Street between Willard Street and Duke Street will have a westbound lane closure to accommodate waterline installation.  
    • Traffic control signs and markings will be used for the Jackson Street westbound detour. 
    • Lane shifts with flaggers will be utilized for traffic control while work is taking place in intersections and at waterline connection locations.
    • Sidewalk traffic will be disrupted.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Planned work hours are 7 AM to 7 PM.
    • No water or sewer service disruptions are anticipated.

Saturday – Sunday January 23-24, 2021:

  • No work will take place on Saturday or Sunday.

Week of January 25, 2021:

  • Willard Street between Blackwell Street and Yancey Street will have a road closure to accommodate sanitary sewer installation.
    • Traffic control signs and markings will be used for the Willard Street detour. 
    • Access to the ATC South Deck via Willard Street will be temporarily closed to accommodate installations.  Detour signs directing traffic to access the deck via Julian Carr will be used.
    • Sidewalk traffic will be disrupted.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Planned work hours are 7 AM to 7 PM.
    • No water or sewer service disruptions are anticipated.
  • Jackson Street between Willard Street and Duke Street will have a westbound lane closure to accommodate waterline installation.  
    • Traffic control signs and markings will be used for the Jackson Street westbound detour. 
    • Lane shifts with flaggers will be utilized for traffic control while work is taking place in intersections and at waterline connection locations.
    • Sidewalk traffic will be disrupted.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Planned work hours are 7 AM to 7 PM.
    • No water or sewer service disruptions are anticipated.
  • Duke Street between Morehead Ave and Jackson Street will have a lane closure to accommodate waterline installation.
    • Traffic control signs and markings will be used for the lane closure. 
    • Sidewalk traffic will be disrupted.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Planned work hours are 7 AM to 7 PM.
    • No water or sewer service disruptions are anticipated.

Saturday – Sunday January 30-31, 2021:

  • No work will take place on Saturday or Sunday.

If you have questions, please email Lisa.Mitchell@durhamnc.gov.

Facebook Twitter Email

Other News in American Tobacco District Waterline Replacement Project Updates

American Tobacco Waterline Replacement

Project Update | March 5

Posted on: March 5, 2021
American Tobacco Waterline Replacement

Project Update | February 26

Posted on: February 26, 2021
American Tobacco Waterline Replacement

Project Update | February 19

Posted on: February 19, 2021
American Tobacco Waterline Replacement

Project Update | February 12

Posted on: February 12, 2021

Project Update | February 5

Posted on: February 5, 2021
American Tobacco Waterline Replacement

Project Update | January 29

Posted on: January 29, 2021
American Tobacco Waterline Replacement

Project Update | January 22

Posted on: January 22, 2021

Project Update | January 8

Posted on: January 8, 2021

Project Update | December 31

Posted on: December 31, 2020

Project Update | December 24

Posted on: December 24, 2020

Project Update | December 18

Posted on: December 18, 2020

Project Update | December 11

Posted on: December 11, 2020

Project Update | December 4

Posted on: December 4, 2020

November 20 | Project Update

Posted on: November 20, 2020

November 13 | Project Update

Posted on: November 13, 2020

November 6 | Project Update

Posted on: November 6, 2020

October 30 | Project Update

Posted on: October 29, 2020

October 23 | Project Update

Posted on: October 23, 2020

Project Update | October 16, 2020

Posted on: October 16, 2020

Project Update | October 9, 2020

Posted on: October 8, 2020

Project Update | October 2, 2020

Posted on: October 2, 2020

Phase 1 Project to Begin October 5, 2020

Posted on: September 25, 2020