American Tobacco District Waterline Replacement Project Updates

Posted on: December 18, 2020

Project Update | December 18

American Tobacco District Waterline Replacement – Phase 1 Project Update and Two-Week Look Ahead

 December 18, 2020

 The City appreciates your ongoing patience with the work along the busy corridors associated with this project.  Additional information regarding this project can be found at: https://durhamnc.gov/2780/American-Tobacco-District-Waterline-Repl.

 Planned Road / Lane Closures will occur as follows:

  • Week of 12/21: 
    • Northbound lane closure of Willard Street between Julian Carr Street and Jackson Street. 
    • Westbound lane closure of Yancey Street between Willard Street and Duke Street. 
    • Westbound lane closure of Jackson Street between Willard Street and Duke Street. 
  • Week of 12/28: 
    • Northbound lane closure of Willard Street between Julian Carr Street and Jackson Street.  
    • Westbound lane closure of Yancey Street between Willard Street and Duke Street. 
    • Westbound lane closure of Jackson Street between Willard Street and Duke Street. 

 Week of December 21, 2020:

  • Willard Street between Julian Carr Street and Jackson Street will have a northbound lane closure to accommodate waterline installation.
    • Traffic control signs and markings will be used for the Willard Street northbound detour. 
    • Lane shifts with flaggers will be utilized for traffic control while work is taking place in intersections and at waterline connection locations.
    • Sidewalk traffic will be disrupted.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Planned work hours are 7 AM to 7 PM.
    • Water service reconnections will be coordinated at least 7 days in advance of planned work.
  • Yancey Street between Willard Street and Duke Street will have a westbound lane closure to accommodate waterline installation.  
    • Traffic control signs and markings will be used for the Yancey Street westbound detour. 
    • Lane shifts with flaggers will be utilized for traffic control while work is taking place in intersections and at waterline connection locations.
    • Sidewalk traffic will be disrupted.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Planned work hours are 7 AM to 7 PM.
    • No water or sewer service disruptions are anticipated.
  • Jackson Street between Willard Street and Duke Street will have a westbound lane closure to accommodate waterline installation.  
    • Note: Westbound Jackson St and Westbound Yancey St will not be closed at the same time.
    • Traffic control signs and markings will be used for the Jackson Street westbound detour. 
    • Lane shifts with flaggers will be utilized for traffic control while work is taking place in intersections and at waterline connection locations.
    • Sidewalk traffic will be disrupted.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Planned work hours are 7 AM to 7 PM.
    • No water or sewer service disruptions are anticipated.

 Thursday – Sunday December 24-27, 2020:

  • No work will take place on Thursday through Sunday.

 Week of December 28, 2020:

  • Willard Street between Julian Carr Street and Jackson Street will have a northbound lane closure to accommodate waterline installation.
    • Traffic control signs and markings will be used for the Willard Street northbound detour. 
    • Lane shifts with flaggers will be utilized for traffic control while work is taking place in intersections and at waterline connection locations.
    • Sidewalk traffic will be disrupted.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Planned work hours are 7 AM to 7 PM.
    • Water service reconnections will be coordinated at least 7 days in advance of planned work.
  • Yancey Street between Willard Street and Duke Street will have a westbound lane closure to accommodate waterline installation.  
    • Traffic control signs and markings will be used for the Yancey Street westbound detour. 
    • Lane shifts with flaggers will be utilized for traffic control while work is taking place in intersections and at waterline connection locations.
    • Sidewalk traffic will be disrupted.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Planned work hours are 7 AM to 7 PM.
    • No water or sewer service disruptions are anticipated.
  • Jackson Street between Willard Street and Duke Street will have a westbound lane closure to accommodate waterline installation.  
    • Note: Westbound Jackson St and Westbound Yancey St will not be closed at the same time.
    • Traffic control signs and markings will be used for the Jackson Street westbound detour. 
    • Lane shifts with flaggers will be utilized for traffic control while work is taking place in intersections and at waterline connection locations.
    • Sidewalk traffic will be disrupted.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Planned work hours are 7 AM to 7 PM.
    • No water or sewer service disruptions are anticipated.

 Friday – Sunday January 1-3, 2021:

  • No work will take place from Friday through Sunday.

 If you have questions, please email Lisa.Mitchell@durhamnc.gov.

Facebook Twitter Email

Other News in American Tobacco District Waterline Replacement Project Updates

American Tobacco Waterline Replacement

Project Update | February 26

Posted on: February 26, 2021
American Tobacco Waterline Replacement

Project Update | February 19

Posted on: February 19, 2021
American Tobacco Waterline Replacement

Project Update | February 12

Posted on: February 12, 2021

Project Update | February 5

Posted on: February 5, 2021
American Tobacco Waterline Replacement

Project Update | January 29

Posted on: January 29, 2021
American Tobacco Waterline Replacement

Project Update | January 22

Posted on: January 22, 2021

Project Update | January 15

Posted on: January 15, 2021

Project Update | January 8

Posted on: January 8, 2021

Project Update | December 31

Posted on: December 31, 2020

Project Update | December 24

Posted on: December 24, 2020

Project Update | December 11

Posted on: December 11, 2020

Project Update | December 4

Posted on: December 4, 2020

November 20 | Project Update

Posted on: November 20, 2020

November 13 | Project Update

Posted on: November 13, 2020

November 6 | Project Update

Posted on: November 6, 2020

October 30 | Project Update

Posted on: October 29, 2020

October 23 | Project Update

Posted on: October 23, 2020

Project Update | October 16, 2020

Posted on: October 16, 2020

Project Update | October 9, 2020

Posted on: October 8, 2020

Project Update | October 2, 2020

Posted on: October 2, 2020

Phase 1 Project to Begin October 5, 2020

Posted on: September 25, 2020