News Flash

American Tobacco District Waterline Replacement Project Updates

Posted on: December 11, 2020

Project Update | December 11

American Tobacco District Waterline Replacement – Phase 1 Project Update and Two-Week Look Ahead

 December 11, 2020

 The City appreciates your ongoing patience with the work along the busy corridors associated with this project.  Additional information regarding this project can be found at: https://durhamnc.gov/2780/American-Tobacco-District-Waterline-Repl.

 Planned Road / Lane Closures will occur as follows:

  • Week of 12/14: 
    • Northbound lane closure of Willard Street between Julian Carr Street and Jackson Street. 
    • Westbound lane closure of Yancey Street between Willard Street and Duke Street. 
    • Westbound lane closure of Jackson Street between Willard Street and Duke Street.  
  • Week of 12/21: 
    • Northbound lane closure of Willard Street between Julian Carr Street and Jackson Street.  
    • Westbound lane closure of Yancey Street between Willard Street and Duke Street. 
    • Westbound lane closure of Jackson Street between Willard Street and Duke Street. 

 Week of December 14, 2020:

  • Willard Street between Julian Carr Street and Jackson Street will have a northbound lane closure to accommodate waterline installation.
    • Traffic control signs and markings will be used for the Willard Street northbound detour. 
    • Lane shifts with flaggers will be utilized for traffic control while work is taking place in intersections and at waterline connection locations.
    • Sidewalk traffic will be disrupted.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Planned work hours are 7 AM to 7 PM.
    • Water service reconnections will be coordinated at least 7 days in advance of planned work.
  • Yancey Street between Willard Street and Duke Street will have a westbound lane closure to accommodate waterline installation.  
    • Traffic control signs and markings will be used for the Yancey Street westbound detour. 
    • Lane shifts with flaggers will be utilized for traffic control while work is taking place in intersections and at waterline connection locations.
    • Sidewalk traffic will be disrupted.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Planned work hours are 7 AM to 7 PM.
    • No water or sewer service disruptions are anticipated.
  • Jackson Street between Willard Street and Duke Street will have a westbound lane closure to accommodate waterline installation.  
    • Note: Westbound Jackson St and Westbound Yancey St will not be closed at the same time.
    • Traffic control signs and markings will be used for the Jackson Street westbound detour. 
    • Lane shifts with flaggers will be utilized for traffic control while work is taking place in intersections and at waterline connection locations.
    • Sidewalk traffic will be disrupted.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Planned work hours are 7 AM to 7 PM.
    • No water or sewer service disruptions are anticipated. 

Saturday – Sunday December 19-20, 2020:

  • No work will take place on Saturday or Sunday.

 Week of December 21, 2020:

  • Willard Street between Julian Carr Street and Jackson Street will have a northbound lane closure to accommodate waterline installation.
    • Traffic control signs and markings will be used for the Willard Street northbound detour. 
    • Lane shifts with flaggers will be utilized for traffic control while work is taking place in intersections and at waterline connection locations.
    • Sidewalk traffic will be disrupted.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Planned work hours are 7 AM to 7 PM.
    • Water service reconnections will be coordinated at least 7 days in advance of planned work.
  • Yancey Street between Willard Street and Duke Street will have a westbound lane closure to accommodate waterline installation.  
    • Traffic control signs and markings will be used for the Yancey Street westbound detour. 
    • Lane shifts with flaggers will be utilized for traffic control while work is taking place in intersections and at waterline connection locations.
    • Sidewalk traffic will be disrupted.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Planned work hours are 7 AM to 7 PM.
    • No water or sewer service disruptions are anticipated.
  • Jackson Street between Willard Street and Duke Street will have a westbound lane closure to accommodate waterline installation.  
    • Note: Westbound Jackson St and Westbound Yancey St will not be closed at the same time.
    • Traffic control signs and markings will be used for the Jackson Street westbound detour. 
    • Lane shifts with flaggers will be utilized for traffic control while work is taking place in intersections and at waterline connection locations.
    • Sidewalk traffic will be disrupted.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Planned work hours are 7 AM to 7 PM.
    • No water or sewer service disruptions are anticipated.

 Thursday – Sunday December 24-27, 2020:

  • No work will take place from Thursday through Sunday.

 If you have questions, please email Lisa.Mitchell@durhamnc.gov.

Facebook Twitter Email

Other News in American Tobacco District Waterline Replacement Project Updates

Project Update | July 30

Posted on: July 30, 2021
American Tobacco Waterline Replacement

Project Update | July 23

Posted on: July 23, 2021
American Tobacco Waterline Replacement

Project Update | July 16

Posted on: July 16, 2021
American Tobacco Waterline Replacement

Project Update | July 9

Posted on: July 9, 2021
American Tobacco Waterline Replacement

Project Update | July 2

Posted on: July 2, 2021
American Tobacco Waterline Replacement

Project Update | June 25

Posted on: June 25, 2021
American Tobacco Waterline Replacement

Project Update | June 18

Posted on: June 18, 2021
American Tobacco Waterline Replacement

Project Update | June 11

Posted on: June 11, 2021
American Tobacco Waterline Replacement

Project Update | June 4

Posted on: June 4, 2021
American Tobacco Waterline Replacement

Project Update | May 28

Posted on: May 28, 2021
American Tobacco Waterline Replacement

Project Update | May 21

Posted on: May 21, 2021
American Tobacco Waterline Replacement

Project Update | May 14

Posted on: May 14, 2021
American Tobacco Waterline Replacement

Project Update | May 7

Posted on: May 7, 2021

Project Update | April 30

Posted on: April 30, 2021
American Tobacco Waterline Replacement

Project Update | April 23

Posted on: April 23, 2021
American Tobacco Waterline Replacement

Project Update | April 16

Posted on: April 16, 2021
American Tobacco Waterline Replacement

Project Update | April 9

Posted on: April 9, 2021
American Tobacco Waterline Replacement

Project Update | April 2

Posted on: April 2, 2021
American Tobacco Waterline Replacement

Project Update | March 26

Posted on: March 26, 2021
American Tobacco Waterline Replacement

Project Update | March 19

Posted on: March 19, 2021
American Tobacco Waterline Replacement

Project Update | March 12

Posted on: March 12, 2021
American Tobacco Waterline Replacement

Project Update | March 5

Posted on: March 5, 2021
American Tobacco Waterline Replacement

Project Update | February 26

Posted on: February 26, 2021
American Tobacco Waterline Replacement

Project Update | February 19

Posted on: February 19, 2021
American Tobacco Waterline Replacement

Project Update | February 12

Posted on: February 12, 2021

Project Update | February 5

Posted on: February 5, 2021
American Tobacco Waterline Replacement

Project Update | January 29

Posted on: January 29, 2021
American Tobacco Waterline Replacement

Project Update | January 22

Posted on: January 22, 2021

Project Update | January 15

Posted on: January 15, 2021

Project Update | January 8

Posted on: January 8, 2021

Project Update | December 31

Posted on: December 31, 2020

Project Update | December 24

Posted on: December 24, 2020

Project Update | December 18

Posted on: December 18, 2020

Project Update | December 4

Posted on: December 4, 2020

November 20 | Project Update

Posted on: November 20, 2020

November 13 | Project Update

Posted on: November 13, 2020

November 6 | Project Update

Posted on: November 6, 2020

October 30 | Project Update

Posted on: October 29, 2020

October 23 | Project Update

Posted on: October 23, 2020

Project Update | October 16, 2020

Posted on: October 16, 2020

Project Update | October 9, 2020

Posted on: October 8, 2020

Project Update | October 2, 2020

Posted on: October 2, 2020

Phase 1 Project to Begin October 5, 2020

Posted on: September 25, 2020