American Tobacco District Waterline Replacement Project Updates

Posted on: October 29, 2020

October 30 | Project Update

Thank you again for your interest in the American Tobacco District Waterline Replacement Project. Here's what you can expect from construction in the first weeks of November. Please note, the northbound lane closure of Willard Street currently in place will be extended to Jackson Street during the coming two weeks. Additional information regarding this project can be found at: https://durhamnc.gov/2780/American-Tobacco-District-Waterline-Repl.

Planned Road / Lane Closures will occur as follows:

  • Week of 11/2: 
    • Northbound lane closure of Willard Street between Julian Carr Street and Jackson Street.  
  • Week of 11/9: 
    • Northbound lane closure of Willard Street between Julian Carr Street and Jackson Street.  

 Week of November 2, 2020:

  • Willard Street between Julian Carr St and Jackson St will have a northbound lane closure to accommodate waterline installation.
    • Traffic control signs and markings will be used for the Willard Street northbound detour. 
    • Lane shifts with flaggers will be utilized for traffic control while work is taking place in intersections and at waterline connection locations.
    • Sidewalk traffic will be disrupted.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Planned work hours are 7 AM to 7 PM.
    • No water or sewer service disruptions are anticipated.

Saturday – Sunday November 7-8, 2020:

  • No work will take place on Saturday or Sunday.

 Week of November 9, 2020:

  • Willard Street between Julian Carr St and Jackson St will have a northbound lane closure to accommodate waterline installation.
    • Traffic control signs and markings will be used for the Willard Street northbound detour. 
    • Lane shifts with flaggers will be utilized for traffic control while work is taking place in intersections and at waterline connection locations.
    • Sidewalk traffic will be disrupted.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Planned work hours are 7 AM to 7 PM.
    • No water or sewer service disruptions are anticipated.

 Saturday – Sunday November 14-15, 2020:

  • No work will take place on Saturday or Sunday.


If you have questions, please email Lisa.Mitchell@durhamnc.gov.

(To subscribe to future updates, select the Notify Me letter icon in the Tools list on the right side of this page. This will take you to a list of all City subscription opportunities. Scroll to the top of the page; you’ll see a prompt to login or subscribe. Enter your email address or phone number, return to the News Flash section, select the letter or phone icon beside the entry for American Tobacco District Waterline Replacement Project Updates, and confirm your subscription by verifying the link sent. You can unsubscribe at any time.)

Facebook Twitter Email

Other News in American Tobacco District Waterline Replacement Project Updates

Project Update | January 15

Posted on: January 15, 2021

Project Update | January 8

Posted on: January 8, 2021

Project Update | December 31

Posted on: December 31, 2020

Project Update | December 24

Posted on: December 24, 2020

Project Update | December 18

Posted on: December 18, 2020

Project Update | December 11

Posted on: December 11, 2020

Project Update | December 4

Posted on: December 4, 2020

November 20 | Project Update

Posted on: November 20, 2020

November 13 | Project Update

Posted on: November 13, 2020

November 6 | Project Update

Posted on: November 6, 2020

October 23 | Project Update

Posted on: October 23, 2020

Project Update | October 16, 2020

Posted on: October 16, 2020

Project Update | October 9, 2020

Posted on: October 8, 2020

Project Update | October 2, 2020

Posted on: October 2, 2020

Phase 1 Project to Begin October 5, 2020

Posted on: September 25, 2020