Buchanan Boulevard Waterline Replacement Project Updates

Posted on: September 19, 2019

Project Update | September 19, 2019

Buchanan Boulevard Waterline Replacement Project Update and Two-Week Look Ahead

September 19, 2019

The City appreciates your ongoing patience with the work along the busy corridors associated with this project. Additional information regarding this project can be found at: http://durhamnc.gov/3617/Buchanan-Blvd-Waterline-Replacement.

Planned Road / Lane Closures will occur as follows:

  • Week of 9/23:
    • Full closure of Buchanan Blvd between W. Main Street and Maxwell Ave.
    • Lane closures with flaggers in Buchanan Blvd between W. Chapel Hill Street and Maxwell Ave. for pavement restoration.
    • Isolated lane closures and traffic shifts in project area for sanitary sewer investigations and rehabilitation.
  • Week of 9/30:
    • Full closure of Buchanan Blvd between W. Main Street and Maxwell Ave.
    • Lane closures with flaggers in Buchanan Blvd between W. Chapel Hill Street and Maxwell Ave. for pavement restoration.
    • Isolated lane closures and traffic shifts in project area for sanitary sewer investigations and rehabilitation.

Saturday – Sunday September 21-22, 2019:

  • No work will take place on Saturday or Sunday.

Week of September 23, 2019:

  • Buchanan Boulevard will be closed in both directions between W. Main Street and Maxwell Ave.
    • Waterline installation and pavement repairs will continue.
    • Traffic control signs and markings will be used for all traffic detours.
    • Sidewalk traffic will be disrupted.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Planned work hours are 7 AM to 7 PM.
  • Buchanan Boulevard will have lane closures with flaggers between W. Chapel Hill Street and Maxwell Ave.
    • Pavement repairs will take place between W. Chapel Hill Street and Maxwell Ave.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Planned work hours are 7 AM to 7 PM.
    • Pavement along W. Chapel Hill Street will be rough and uneven as final pavement repairs are being completed.
  • Isolated lane closures and shifts lasting several hours will be required in the project area to accommodate sanitary sewer investigations and sidewalk installation.
    • Traffic control signs and markings will be used for all traffic detours.
    • Sanitary sewer lining and dye testing will take place in Gattis, Exum, Burch, Wilkerson, and Jackson streets during daytime hours. Notices will be distributed to affected customers prior to work taking place.

Saturday – Sunday September 28-29, 2019:

  • No work will take place on Saturday or Sunday.

Week of September 30, 2019:

  • Buchanan Boulevard will be closed in both directions between W. Main Street and Maxwell Ave.
    • Waterline installation and pavement repairs will continue.
    • Traffic control signs and markings will be used for all traffic detours.
    • Sidewalk traffic will be disrupted.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Planned work hours are 7 AM to 7 PM.
  • Buchanan Boulevard will have lane closures with flaggers between W. Chapel Hill Street and Maxwell Ave.
    • Pavement repairs will take place between W. Chapel Hill Street and Maxwell Ave.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Planned work hours are 7 AM to 7 PM.
    • Pavement along W. Chapel Hill Street will be rough and uneven as final pavement repairs are being completed.
  • Isolated lane closures and shifts lasting several hours will be required in the project area to accommodate sanitary sewer investigations and sidewalk installation.
    • Traffic control signs and markings will be used for all traffic detours.
    • Sanitary sewer lining and dye testing will take place in Gattis, Exum, Burch, Wilkerson, and Jackson streets during daytime hours. Notices will be distributed to affected customers prior to work taking place.

Additional information regarding this work can be found at www.DurhamOperationGreenlight.org. Find more information about all of the department’s current projects at www.DurhamWaterProjects.org. If you have questions, please email DowntownLoopWRP@DurhamNC.gov.


Facebook Twitter Email

Other News in Buchanan Boulevard Waterline Replacement Project Updates

Project Update | October 17, 2019

Posted on: October 17, 2019

Project Update | October 10, 2019

Posted on: October 10, 2019

Project Update | October 3 , 2019

Posted on: October 3, 2019

Project Update | September 26, 2019

Posted on: September 26, 2019

Project Update | September 12, 2019

Posted on: September 12, 2019

Project Update | September 5, 2019

Posted on: September 5, 2019

Project Update | August 29, 2019

Posted on: August 29, 2019

Project Update | August 22, 2019

Posted on: August 22, 2019

Project Update | August 15, 2019

Posted on: August 15, 2019

Project Update | August 8, 2019

Posted on: August 8, 2019

Project Update | August 1, 2019

Posted on: August 1, 2019

Project Update | July 25, 2019

Posted on: July 25, 2019

Project Update | July 18, 2019

Posted on: July 18, 2019

Project Update | July 11, 2019

Posted on: July 11, 2019

Project Update | July 3, 2019

Posted on: July 3, 2019

Project Update | June 27, 2019

Posted on: June 27, 2019

Project Update | June 20, 2019

Posted on: June 20, 2019

Project Update | June 13, 2019

Posted on: June 13, 2019

Project Update | June 6, 2019

Posted on: June 6, 2019

Project Update | May 30, 2019

Posted on: May 30, 2019

Project Update | May 23, 2019

Posted on: May 23, 2019

Project Update | May 16, 2019

Posted on: May 16, 2019

Project Update | May 9, 2019

Posted on: May 9, 2019

Project Update | May 2, 2019

Posted on: May 2, 2019

Project Update | April 25, 2019

Posted on: April 25, 2019

Project Update | April 18, 2019

Posted on: April 18, 2019

Project Update | April 11, 2019

Posted on: April 11, 2019

Project Update | April 4, 2019

Posted on: April 4, 2019

Project Update | March 28, 2019

Posted on: March 28, 2019

Project Update | March 21, 2019

Posted on: March 21, 2019

Project Update | March 14, 2019

Posted on: March 14, 2019

Project Update | March 7, 2019

Posted on: March 7, 2019

Project Update | February 28, 2019

Posted on: February 28, 2019

Project Update | February 21, 2019

Posted on: February 21, 2019

Project Update | February 14, 2019

Posted on: February 14, 2019

Project Update | February 7, 2019

Posted on: February 7, 2019

Project Update | January 31, 2019

Posted on: January 31, 2019

Project Update | January 24, 2019

Posted on: January 24, 2019

Project Update | January 17, 2019

Posted on: January 17, 2019

Project Update | January 11, 2019

Posted on: January 11, 2019