Durham Central Park Waterline Replacement Project Updates

Posted on: January 31, 2019

Project Update | January 31, 2019

Central Park Waterline Replacement Project Update and Two-Week Look Ahead

January 31, 2019

The City appreciates your ongoing patience with the work along the busy corridors associated with the Central Park Waterline Replacement Project. Additional information regarding this project can be found at: http://durhamnc.gov/1251/Durham-Central-Park-Waterline-Replacement.

Planned Road / Lane Closures will occur as follows:

  • Week of 2/4:
    • Intersection of Rigsbee Avenue and Seminary Avenue will be closed.
    • Rigsbee Avenue will be reduced to one lane northbound between West Morgan Street and Hunt Street.
    • Intersection of Foster Street and Seminary Avenue will be temporarily closed as sanitary sewer work continues.
    • Corporation Street between Rigsbee Avenue and Mangum Street may be reduced to one lane as sanitary sewer work continues.
    • Geer Street will be reduced to one lane between Washington Street and Foster Street.
    • The intersection of Washington Street and Geer Street will be closed. Business parking will be accessible.
    • Washington Street between Monmouth Avenue and Trinity Avenue will be reduced to one lane northbound as water line installation begins.
    • The intersection of Washington Street and Monmouth Avenue will be temporarily closed as water line installation begins.
  • Week of 2/11:
    • Intersection of Rigsbee Avenue and Seminary Avenue will be closed.
    • Rigsbee Avenue will be reduced to one lane northbound between West Morgan Street and Hunt Street.
    • Intersection of Foster Street and Seminary Avenue will be temporarily closed as sanitary sewer work continues.
    • Corporation Street between Rigsbee Avenue and Mangum Street may be reduced to one lane as sanitary sewer work continues.
    • Geer Street will be reduced to one lane between Washington Street and Foster Street.
    • Washington Street between Monmouth Avenue and Trinity Avenue will be reduced to one lane northbound as water line installation continues.
    • Washington Street between Geer Street and West Corporation Street will be closed as sanitary sewer work begins.

Week of February 4, 2019:

  • Rigsbee Avenue will be reduced to one lane as sanitary sewer work continues.
    • Traffic control signs and markings will be used for all traffic detours.
    • Sidewalk traffic will be disrupted.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • On-street parking will be closed in work areas.
    • Planned work hours are 7 AM to 6 PM.
    • Residents and business owners will be contacted in advance of any service disruptions.
  • Foster Street at Seminary Avenue will be reduced to one lane as sanitary sewer work continues.
    • Traffic control signs and markings will be used for all traffic detours.
    • Sidewalk traffic will be disrupted.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • On-street parking will be closed in work areas.
    • Planned work hours are 7 AM to 6 PM.
    • Residents and business owners will be contacted in advance of any service disruptions.
  • West Corporation Street will be reduced to one lane as sanitary sewer work continues.
    • Traffic control signs and markings will be used for all traffic detours.
    • Sidewalk traffic will be disrupted.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • On-street parking will be closed in work areas.
    • Planned work hours are 7 AM to 6 PM.
    • Residents and business owners will be contacted in advance of any service disruptions.
  • Geer Street will be reduced to one lane as sanitary sewer work continues.
    • Traffic control signs and markings will be used for all traffic detours.
    • Sidewalk traffic will be disrupted.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • On-street parking will be closed in work areas.
    • Planned work hours are 7 AM to 6 PM.
    • No water or sewer service disruptions are anticipated.
  • Washington Street at Geer Street will be closed as sanitary sewer work continues.
    • Traffic control signs and markings will be used for all traffic detours.
    • Sidewalk traffic will be disrupted.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • On-street parking will be closed in work areas.
    • Planned work hours are 7 AM to 6 PM.
    • No water or sewer service disruptions are anticipated.
  • Washington Street at Monmouth Avenue will be temporarily closed as water line work continues.
    • Traffic control signs and markings will be used for all traffic detours.
    • Sidewalk traffic will be disrupted.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • On-street parking will be closed in work areas.
    • Planned work hours are 7 AM to 6 PM.
    • No water or sewer service disruptions are anticipated.
  • Washington Street between Monmouth Avenue and West Trinity Street will be reduced to one lane as water line work begins.
    • Traffic control signs and markings will be used for all traffic detours.
    • Sidewalk traffic will be disrupted.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • On-street parking will be closed in work areas.
    • Planned work hours are 7 AM to 6 PM.
    • No water or sewer service disruptions are anticipated.

Saturday – Sunday February 9-10, 2019:

  • No work is scheduled for this weekend.

Week of February 11, 2019:

  • Rigsbee Avenue will be reduced to one lane as water line work continues.
    • Traffic control signs and markings will be used for all traffic detours.
    • Sidewalk traffic will be disrupted.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • On-street parking will be closed in work areas.
    • Planned work hours are 7 AM to 6 PM.
    • Residents and business owners will be contacted in advance of any service disruptions.
  • Foster Street at Seminary Avenue will be reduced to one lane as sanitary sewer work continues.
    • Traffic control signs and markings will be used for all traffic detours.
    • Sidewalk traffic will be disrupted.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • On-street parking will be closed in work areas.
    • Planned work hours are 7 AM to 6 PM.
    • Residents and business owners will be contacted in advance of any service disruptions.
  • Corporation Street will be reduced to one lane as sanitary sewer work continues.
    • Traffic control signs and markings will be used for all traffic detours.
    • Sidewalk traffic will be disrupted.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • On-street parking will be closed in work areas.
    • Planned work hours are 7 AM to 6 PM.
    • Residents and business owners will be contacted in advance of any service disruptions.
  • Geer Street will be reduced to one lane as sanitary sewer work continues.
    • Traffic control signs and markings will be used for all traffic detours.
    • Sidewalk traffic will be disrupted.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • On-street parking will be closed in work areas.
    • Planned work hours are 7 AM to 6 PM.
    • No water or sewer service disruptions are anticipated.
  • Washington Street between Monmouth Avenue and West Trinity Street will be reduced to one lane as water line work continues.
    • Traffic control signs and markings will be used for all traffic detours.
    • Sidewalk traffic will be disrupted.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • On-street parking will be closed in work areas.
    • Planned work hours are 7 AM to 6 PM.
    • No water or sewer service disruptions are anticipated.
  • Washington Street between West Corporation Street and Geer Street will be closed as sanitary sewer work begins.
    • Traffic control signs and markings will be used for all traffic detours.
    • Sidewalk traffic will be disrupted.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • On-street parking will be closed in work areas.
    • Planned work hours are 7 AM to 6 PM.
    • No water or sewer service disruptions are anticipated.

Saturday – Sunday February 16-17, 2019:

  • No work is scheduled for this weekend.

Additional information regarding this work can be found at www.DurhamOperationGreenlight.org. Find more information about all of the department’s current projects at www.DurhamWaterProjects.org. If you have questions, please email DowntownLoopWRP@DurhamNC.gov.

Facebook Twitter Email

Other News in Durham Central Park Waterline Replacement Project Updates

Project Update | September 19, 2019

Posted on: September 19, 2019

Project Update | September 12, 2019

Posted on: September 12, 2019

Project Update | September 5, 2019

Posted on: September 5, 2019

Project Update | August 29 , 2019

Posted on: August 29, 2019

Project Update | August 22,2019

Posted on: August 23, 2019

Project Update | August 15, 2019

Posted on: August 15, 2019

Project Update | August 8, 2019

Posted on: August 8, 2019

Project Update | August 1, 2019

Posted on: August 1, 2019

Project Update | July 25, 2019

Posted on: July 25, 2019

Project Update | July 18, 2019

Posted on: July 18, 2019

Project Update | July 11, 2019

Posted on: July 11, 2019

Project Update | July 3, 2019

Posted on: July 3, 2019

Project Update | June 27, 2019

Posted on: June 27, 2019

Project Update | June 20, 2019

Posted on: June 20, 2019

Project Update | June 13, 2019

Posted on: June 13, 2019

Project Update | June 6, 2019

Posted on: June 6, 2019

Project Update | May 30, 2019

Posted on: May 30, 2019

Project Update | May 23, 2019

Posted on: May 24, 2019

Project Update | May 16, 2019

Posted on: May 16, 2019

Project Update | May 9, 2019

Posted on: May 9, 2019

Project Update | May 2, 2019

Posted on: May 2, 2019

Project Update | April 25, 2019

Posted on: April 25, 2019

Project Update | April 18, 2019

Posted on: April 18, 2019

Project Update | April 11, 2019

Posted on: April 11, 2019

Project Update | April 4, 2019

Posted on: April 4, 2019

Project Update | March 28, 2019

Posted on: March 28, 2019

Project Update | March 21, 2019

Posted on: March 21, 2019

Project Update | March 14, 2019

Posted on: March 14, 2019

Project Update | March 7, 2019

Posted on: March 7, 2019

Project Update | February 28, 2019

Posted on: February 28, 2019

Project Update | February 21, 2019

Posted on: February 21, 2019

Project Update | February 14, 2019

Posted on: February 14, 2019

Project Update | February 7, 2019

Posted on: February 7, 2019

Project Update | January 17, 2019

Posted on: January 17, 2019

Project Update | January 10, 2019

Posted on: January 10, 2019

Project Update | January 3, 2019

Posted on: January 3, 2019

Project Update | December 19, 2018

Posted on: December 19, 2018

Project Update | December 13, 2018

Posted on: December 13, 2018

Project Update | December 6, 2018

Posted on: December 6, 2018

Project Update | November 29, 2018

Posted on: November 29, 2018

Project Update | November 22, 2018

Posted on: November 26, 2018

Project Update | October 15, 2018

Posted on: November 15, 2018

Project Update | November 8, 2018

Posted on: November 8, 2018

Project Update | October 2, 2018

Posted on: November 2, 2018

Project Update | October 25, 2018

Posted on: October 25, 2018

Project Update | October 18, 2018

Posted on: October 18, 2018

Project Update | October 11, 2018

Posted on: October 11, 2018

Project Update | October 4, 2018

Posted on: October 4, 2018

Project Update | September 27, 2018

Posted on: September 27, 2018