2015 Sidewalk Construction Administration (SW-38C)

Project Manager
Clint Blackburn, EI
Phone: 919-560-4326, ext. 30245

This project has been accepted into the Small Local Business Enterprise Program. Only certified SLBEs will be considered for this project.

Project Description
This is a Request for Qualifications (RFQ) from qualified firms to provide construction administration services for the 2015 Sidewalk Repair project in Durham along Ash Street, Guthrie Avenue, and Buchanan Boulevard.

Project Schedule
  • Advertisement: - Monday, February 9, 2015
  • Pre-Submittal Meeting: - Thursday, February 19, 2015, 8:30 a.m.
  • Submittals Due: - Tuesday, February 24, 2015
  • Anticipated Notice to Proceed: - June, 2015
Project Status
Submittals were received on February 24, 2015 from the following firms:
  • Bree & Associates, Inc.
  • Coulter Jewell Thames P.A.
The City of Durham will proceed with interviews.