PROJECT DESCRIPTION
This project includes repaving and improving drainage conditions along Durham's trails listed below:.

  • Ellerbee Creek Trail Phase 1
  • Ellerbee Creek Trail Phase 2
  • Rock Quarry Spur 
  • ATT- Phase D
  • Riddle Road Spur Trail
  • West Ellerbe Creek Trail
  • Warren Creek Trail 
  • Rocky Creek Greenway
  • South Ellerbe Creek Trail (1995)
  • Renaissance Parkway Sidepath
  • New Hope Creek Trail 
  • Sandy Creek Trail

PROJECT SCHEDULE
The following schedule is estimated and may change.

  • Advertisement:  April 22, 2021
  • Pre-Bid Meeting: Wednesday, May 5, 2021, @ 11;00 AM. 
  • Bid Opening: Friday, May 21, 2021 @ 1;00 PM. 
  • Anticipated Construction Start Date: August 2021
  • Anticipated Contract Completion:  December 2022. 

PROJECT Status
The contract is being advertised.  

The bid-opening Conference will be on Friday, May 21, 2021, @ 1 PM. A link for the virtual meeting will be posted soon.