Project Manager
Mike Boyd, MScM
Phone: (984) 227- 4486
Project Description
This project involves the furnishing of all materials, labor, equipment, tools, etc. unless otherwise specified, for the complete installation of sidewalk, curb and gutter (concrete & granite), driveway apron and brick pavers at various locations within the City of Durham where Water & Sewer repairs were performed.
Project Schedule
- Advertisement: June 17, 2019
- Pre-Bid Meeting: July 3, 2019
- Bid Opening: July 18, 2019
- Pre-Construction Meeting: December 2019
- Construction Start: December, 2019
- Construction Completion: September, 2020
Project Status
Project is complete.
Service request:
Click or call 919-560-1200