ST-314 Pavement Condition Survey 2021

Project Manager


Bayan Alzubi, EI
Phone: 919-560-4326, ext. 30296

Project Description


The project consists of a field survey of the pavement condition on all of the City streets.  

A PCI study is generally performed every four to five years to assess the condition of streets and develop pavement repair recommendations. These PCI ratings in combination with other data, field investigations and engineering judgment will be used to develop the City’s annual asphalt maintenance program.
 


 

PROJECT SCHEDULE

  • Pre-Submittal Meeting: January 27, 2021 
  • Last Date for Receipt of Proposals: February 12, 2021
  • City Council Award: May 17, 2021
  • Contract Start Date: July 1, 2021
  • Anticipated Contract Completion: October 2021

Project Status

 

The Contract has been awarded to Roadway Asset Services, LLC.