N. Roxboro Street Sidewalk 2020 (SW-41)

Project Manager


Kitty Thomas
Phone: 919-560-4326 ext. 30218

Project Description


This project involves the construction of sidewalk along N. Roxboro Street from Pacific Avenue to Murray Avenue. This project will also construct associated curb ramps. This project will provide a safer route for pedestrians along N. Roxboro street. 

Project Schedule


  • Advertisement: November 10, 2020
  • Pre-Bid Meeting: November 23, 2020 @ 2:00 PM via Zoom meeting : https://us02web.zoom.us/j/84274688550
  • Bid OpeningDecember 11, 2020 @ 2:00 PM via Zoom meeting
  • Anticipated Construction Start: March 2021
  • Anticipated Construction Completion: September 2021

Project Status


This project is now advertised. Prospective bidders are encouraged to attend the virtual Pre-bid meeting on November 23, 2020 at 2 PM via zoom https://us02web.zoom.us/j/84274688550 .