2021 Bradford Circle Drainage Improvements (SD-2021-01)​

Project Manager
Antwon Williams, PE
Phone: 919-560-4326, ext. 30254


Project Status


The project is proposed to begin construction in the Spring of 2021. Construction Drawings for the Bradford Circle Drainage Improvements project have been approved. Acquisitions of permanent drainage and construction easements are also complete. Sealed bids were opened on January 28, 2021. The project was awarded to Roadworks Construction Company, LLC. Construction began on May 6, 2021. The project is anticipated to be completed by October 2021.

Key Project Dates


  • Advertisement: November 30, 2020
  • Pre-Bid Conference: December 15, 2020
  • Bid Opening: January 28, 2021
  • Notice to Proceed: May 3, 2021
  • Substantial Completion: August 18, 2021
  • Anticipated Completion: October 31, 2021

Project Description


The project involves the furnishing of all materials, labor, equipment, tools, etc. unless otherwise specified, for the complete installation of repairs, rehabilitation, and improvements of the stormwater drainage system along the Bradford Circle right-of-way and adjacent properties. Currently Bradford Circle is a gravel road. The gravel road surface will be replaced with asphalt and pervious concrete pavement along with the installation of sidewalk.