ST-303 Pavement Preservation 2020

Project Manager


Clint Blackburn
Phone: 919-560-4326, ext. 30245

Project Description


This project involves the furnishing of all materials, labor, equipment, tools, etc. unless otherwise specified, for the preservation of streets. 

This project will be microsurfacing, cape sealing, pavement repair, and crack sealing of streets. 

Project Schedule


  • Advertisement: October 10, 2019
  • Pre-Bid Meeting: October 24, 2019 at 10:00 AM
  • Bid Opening:  November 7, 2019 at 10:00 AM
  • Re-Advertisement: November 22, 2019
  • Bid Opening:  December 4, 2019 at 2:00 PM
  • Begin Construction: February 2020

Project Status


The work in ST-303 was less expensive that budget, so we have been able to add additional neighborhoods to the project. The additional vicinity maps are on the right side of the page. Please see the Slurry Pavers project website for the project schedule and information about the preservation work that they will be doing. www.neighborhoodslurry.com/Durham