ST-303 Pavement Preservation 2020

Project Manager


Clint Blackburn
Phone: 919-560-4326, ext. 30245

Project Description


This project involves the furnishing of all materials, labor, equipment, tools, etc. unless otherwise specified, for the preservation of streets. 

This project will be microsurfacing, cape sealing, pavement repair, and crack sealing of streets. 

Project Schedule


  • Advertisement: October 10, 2019
  • Pre-Bid Meeting: October 24, 2019 at 10:00 AM
  • Bid Opening:  November 7, 2019 at 10:00 AM
  • Re-Advertisement: November 22, 2019
  • Bid Opening:  December 4, 2019 at 2:00 PM
  • Begin Construction: February 2020

Project Status


Patching will begin March 9th in preparation of Microsurfacing in April.  A schedule will be posted in the next week showing the approximately when work will occur.