Project Description


This project involves the furnishing of all materials, labor, equipment, tools, etc. unless otherwise specified, for the preservation, repair, and repaving of various streets throughout the City of Durham. 

For information on pavement preservation techniques, see the links on the right. 

Project Schedule


  • Advertisement: September 26, 2019
  • Pre-Bid Meeting: October 10, 2019 at 2:00 PM
  • Bid Opening: October 25, 2019 at 10:00 AM
  • City Council Approval: December 17, 2019
  • Anticipated Construction Start: April 1, 2020
  • Anticipated Construction Completion:  July 2020

Project Status


The Bid Opening was held on October 25, 2019.  The following companies submitted bids:
Blythe Construction
Barnhill Contracting
Carolina Sunrock
Fred Smith Company (Apparent Low Bidder)