2020 Buckingham Road Culvert Replacement (SD-2020-03)​

Project Manager


Antwon Williams, PE
Phone: 919-560-4326, ext. 30254


Project Status


Visco Transportation Corporation has been awarded this construction contract.  The Notice to Proceed date is May 1, 2020.

Key Project Dates


  • Advertisement: December 18, 2019
  • Pre-Bid Conference: January 6, 2020
  • Bid Opening: January 29, 2020
  • Notice to Proceed: May 1, 2020

Project Description


The project involves the furnishing of all materials, labor, equipment, tools, etc. unless otherwise specified, for the complete replacement storm drainage culvert where Buckingham Road intersects Tributary C of Third Fork Creek.