2020 Buckingham Road Culvert Replacement (SD-2020-03)​

Project Manager

Dana P Hornkohl, PE
Phone: 919-560-4326, ext. 30246


Project Status


This construction contract was advertised on December 18, 2019.  A Pre-Bid Conference was held on January 6, 2020 (minutes).  Addendum No. 1 was issued on January 8, 2020.  Addendum No. 2 was issued on January 20, 2020.  The Bid Opening will be held on January 29, 2020, 1:30 pm, in City (101 City Hall Plaza) in the Third Floor Conference Room.

Project information is available for download to the right.  Please send an e-mail to the project manager if you intend to submit a bid on this project.

Note: A similar culvert replacement is being advertised for construction on the same schedule, Alpine Road Culvert Replacement (SD-2020-04).

Key Project Dates


  • Advertisement: December 18, 2019
  • Pre-Bid Conference: January 6, 2020, 1:30 pm
  • Bid Opening: January 29, 2020, 1:30 pm
  • Notice to Proceed: March 2020 (Anticipated)

Project Description


The project involves the furnishing of all materials, labor, equipment, tools, etc. unless otherwise
specified, for the complete replacement storm drainage culvert where Buckingham Road intersects Tributary C of Third Fork Creek.