Project Manager
Mike Boyd, MScM
Phone: (984) 227- 4486
Project Description
This project involves the furnishing of all materials, labor, equipment, tools, etc. unless otherwise specified, for the complete installation of sidewalk, curb and gutter (concrete & granite), driveway apron and brick pavers at various locations within the City of Durham where Water & Sewer repairs were performed.
Project Schedule
- Bid Proposal Due Date: August 9, 2019
- Kickoff and Pre-Construction Meetings: Dec. 2019
- Project Start: December, 2019
- Project Completion: September, 2020
Project Status
This project is complete.
Service request:
Click or call 919-560-1200