SW-75C Inspections for Upcoming PWOC Concrete Repair Project

Project Manager


Mike Boyd
Phone: (984) 227- 4486

Project Description



This project involves the furnishing of all materials, labor, equipment, tools, etc. unless otherwise specified, for 
the complete installation of sidewalk, curb and gutter (concrete & granite), driveway apron and brick pavers at various locations within the City of Durham where Water & Sewer repairs were performed.

Project Schedule

 
  • Bid Proposal Due Date:  August 9, 2019
  • Anticipated Construction Start: December, 2019
  • Anticipated Construction Completion: August, 2020

Project Status

 
Evaluating Bid Proposals