Project Description
This project involves the furnishing of all materials, labor, equipment, tools, etc. unless otherwise specified, for the construction/stabilization of the slope on Swift Avenue in the City of Durham.
Project Schedule
- Advertisement: July 1, 2019
- Pre-Bid Meeting: July 16, 2019
- Bid Opening: July 31, 2019
- Construction Start: September 2019
- Construction Completion: November 2019
Project Status
This project has been completed.