2019 Stormwater Infrastructure Repairs (SD-2019-02)

Project Manager


Yi Wang, P.E.
Phone: 919-560-4326, ext. 30244


Project Status



Beginning on August 7, 2019, Arnette Avenue between Yancey Street and Parker Street will be closed to through traffic and will remain closed until the repair work is complete. This area will be open to local traffic only and on-street parking will not be available. Construction is expected to take between three to four weeks depending on weather conditions.

Key Project Dates

  • Advertisement: September 6, 2018 
  • Pre-Bid Conference: September 20, 2018 
  • Bid Opening: October 8, 2018 
  • Notice to Proceed: January 22, 2019

Project Description


The project involves the furnishing of all materials, labor, equipment, tools, etc. unless otherwise specified, for the complete installation of the repairs of stormwater drainage infrastructure systems at various project site locations throughout the City of Durham.

Outstanding Project Sites

  • Arnette Avenue

Completed Project Sites


  • Cobb Street
  • Dupree Street 
  • East Forest Hills Boulevard
  • Proctor Street 
  • Steele Avenue