2018 Trenchless Pipe Repairs (SD-2018-03)​

Project Manager

Dana P Hornkohl, PE
Phone: 919-560-4326, ext. 30246


Project Status


The initial five sites identified in the contract were completed in March 2019.  An additional three sites are anticipated to be completed by October 2019.  This work is being performed by Prism Contractors, Inc.

Key Project Dates


  • Advertisement: April 13, 2018
  • Pre-Bid Conference: April 26, 2018
  • Bid Opening: May 15, 2018
  • Notice to Proceed: November 1, 2018

Project Description


The project includes the furnishing of all materials, labor, equipment, tools, etc. unless otherwise specified, for the complete installation of cured-in-place pipe (CIPP) lining of existing storm drainage pipes throughout the City of Durham.

Outstanding Project Sites


  • Durham Area Transit Authority
  • Hillandale Golf Course Hole No. 13
  • Travis Circle Sinnott Circle

Completed Project Sites


  • Beechwood Cemetery
  • Hillandale Golf Course Hole No. 3A
  • Hillandale Golf Course Hole No. 4
  • Technology Drive
  • Wrightwood Avenue