Project Manager
Neil Allen
Phone: 919-471-3581
Project Description
This project involves the design of sidewalks on one side of Raynor Street from N. Miami to Hardee Street. Total length is 0.3 miles. The budget for the project is $364,435
The project vicinity is shown to the right under Project Information. The improvements include new sidewalks and accessible ramps.
Project Schedule
- Design Completed: November 2019
- Anticipated Right-of-Way Completion: July 2021
- Anticipated Bid Advertisement: September 2021
- Anticipated Construction Start: February 2022
- Anticipated Construction Completion: January 2023
Project Status
Ramey Kemp and Associates of Raleigh, NC has been hired as the design firm to prepare plans, obtain permits, and hold informational meetings with stakeholders. They began data collection in February,2018 and currently are in 90% design phase of the project.
The goal of the project is to improve pedestrian accommodations and the proposed improvements include curbs and gutters, ramps, and sidewalks.
Service request:
Click or call 919-560-1200