Project Description


This project involves the design of sidewalks on both sides of LaSalle Street from Kangaroo Drive to Hillsborough Rd and on one side from Hillsborough Rd. to Sprunt Ave.    The total length is 0.7 miles and the design project budget is $201,440.

The project vicinity is shown to the right under Project Information. The improvements include new sidewalks and accessible ramps.
 

Project Schedule

  • Anticipated Design Completion:  January 2020
  • Anticipated Right-of-Way Completion:  March 2021
  • Anticipated Bid Advertisement:  February 2022 
  • Anticipated Construction Start:  July 2022
  • Anticipated Construction Completion:  September 2023


Project Status


SEPI Engineering of Raleigh, NC has been hired as the design firm to prepare plans, obtain permits, and hold informational meetings with stakeholders.  They began data collection in February,2018 and currently are in 25% design phase of the project. 

The first community input meeting was held Tuesday January 15th from 6:30 p.m. to 8:30 p.m. at E.K. Powe Elementary School Cafeteria, located at 913 Ninth Street, Durham. The public was able to review the 25% design plans, ask questions of City staff, and provide input before the City completes the final design plans.  

The second community input meeting is scheduled for Tuesday July 23rd from 4:30 p.m. to 7:30 p.m. at the E.K. Powe Elementary School Cafeteria, located at 913 9th Street. Residents will be able to review the 65% design plans showing right-of-way, temporary and permanent easements, ask questions of Public Works staff, and provide input before the department completes the final design plans.