Design Services for LaSalle Street Sidewalk  (SW-52D)

Project Manager

Lee Murphy, PE
Phone: 919-560-4326, ext. 30208

Project Description

This project involves the design of sidewalks on both sides of LaSalle Street from Kangaroo Drive to Hillsborough Rd and on one side from Hillsborough Rd. to Sprunt Ave.    The total length is 0.7 miles and the design project budget is $201,440.

The project vicinity is shown to the right under Project Information. The improvements include new sidewalks and accessible ramps.

Project Schedule

  • Anticipated Design Completion:  March 2019
  • Anticipated Right-of-Way Completion:  September 2019
  • Anticipated Bid Advertisement:  june 2020 
  • Anticipated Construction Start:  November 2020
  • Anticipated Construction Completion:  October 2021

Project Status

SEPI Engineering of Raleigh, NC has been hired as the design firm to prepare plans, obtain permits, and hold informational meetings with stakeholders.  They began data collection in February,2018 and currently are in the location and survey phase of the project.