Design Services for NC 54 Sidewalk  (SW-51D)

Project Manager


David Cates, PE
Phone: 919-560-4326, ext. 30208

Project Description


This project involves the design of sidewalk on the south side of NC-54 from NC HWY-55 east to the RTP western limit.  The total length is 0.4 miles and the design project budget is $94,169. 

The project vicinity is shown to the right under Project Information. The improvements include new sidewalks and accessible ramps.
 

Project Schedule

  • Anticipated Design Completion:  January 2019
  • Anticipated Right-of-Way Completion:  July 2019
  • Anticipated Bid Advertisement:  April 2020 
  • Anticipated Construction Start:  September 2020
  • Anticipated Construction Completion:  May 2021


Project Status


Davenport Engineering of Raleigh, NC has been hired as the design firm to prepare plans, obtain permits, and hold informational meetings with stakeholders.  They began data collection in February, 2018 and currently are in 25% design phase of the project.