Design Services for Cornwallis Road Sidewalk Bicycle Facilities (SW-45D)

Project Manager


Neil Allen
Phone: 919-471-3581

Project Description


This project involves the design of sidewalks and bicycle facilities on Cornwallis Road from Old Chapel Hill Road to South Roxboro Street.  The total length is 1.2 miles and the design project budget is $533,381. 

The improvements include sidewalks and bicycle facilities.  Final designs are now underway and will be added to this web site when available.
  
 

Project Schedule

  • Anticipated Design Completion:  April 2020
  • Anticipated Right-of-Way Completion:  August 2021
  • Anticipated Bid Advertisement:  October 2021 
  • Anticipated Construction Start:  March 2022
  • Anticipated Construction Completion:  July 2023


Project Status


Alta Planning+Design of Durham, NC has been hired as the design firm to prepare plans, obtain permits, and hold informational meetings with stakeholders.  They began data collection in August 2017. The first community input meeting information can be accessed under project information to the right.  The Meeting Maps for the 03/21/2018 meeting and the Meeting Comment Form are also under Project Information. The comment period ends April 4, 2018.