Design Services for Hillandale Road Sidewalk and Bicycle Facilities (SW-46D)

Project Manager


David Cates, PE
Phone: 919-560-4326, ext. 30208

Project Description


This project involves the design of sidewalks and bicycle facilities on Hillandale Road from I-85 to NC-147. The total length is 1.1 miles and the design project budget is $457,123. 

The improvements include sidewalks and bicycle facilities.  Final designs are now underway and will be added to this web site when available.
 

Project Schedule

  • Anticipated Design Completion:  December 2020
  • Anticipated Right-of-Way Completion:  January 2022
  • Anticipated Bid Advertisement:  June 2022
  • Anticipated Construction Start:  January 2023
  • Anticipated Construction Completion:  March 2024


Project Status


Ramey Kemp and Associates of Raleigh, NC has been employed as the design firm to prepare plans, obtain permits, and hold informational meetings with stakeholders. They began survey and data collection in July, 2017. The first community input meeting was held in January of 2018. The second community input meeting was held June 18th, 2018. The city hosted the third and final community input meeting on Thursday, November 29th, 2018 from 6:30 PM to 8:30 PM in the Media Center, Room 226 at E.K. Powe located at 913 9th St, Durham, NC 27705 where the community viewed the current design and offered comments. Currently Ramey Kemp and the city is awaiting NCDOT's permission to move forward with the right-of-way acquisition phase of the project.