Design Services for Hillandale Road Sidewalk and Bicycle Facilities (SW-46D)

Project Manager


David Cates, PE
Phone: 919-560-4326, ext. 30208

Project Description


This project involves the design of sidewalks and bicycle facilities on Hillandale Road from I-85 to NC-147. The total length is 1.1 miles and the design project budget is $457,123. 

The improvements include sidewalks and bicycle facilities.  Final designs are now underway and will be added to this web site when available.
 

Project Schedule

  • Anticipated Design Completion:  October 2018
  • Anticipated Right-of-Way Completion:  April 2019
  • Anticipated Bid Advertisement:  January 2020 
  • Anticipated Construction Start:  June 2020
  • Anticipated Construction Completion:  May 2021


Project Status


Note: Change of Venue and time for June 18, 2018 Community meeting. Read "Meeting Notice" under Project Information.

Ramey Kemp and Associates of Raleigh, NC has been employed as the design firm to prepare plans, obtain permits, and hold informational meetings with stakeholders. They began survey and data collection in July, 2017 and currently are in the (30%) design stage of the project. The first community input meeting was held in January of 2018. The second community input meeting is 
scheduled for June 18th, 2018 and the press release for the meeting can be accessed under 
project information to the right titled "SW-46D Community Input Meeting (6/18/2018)". The preferred option meeting map and comment form appear to the right under Project Information. The comment period ends July 2, 2018.