2018 Sidewalk Repairs (SW-62)

Project Manager


Allison Molleson, EI
Phone: 919-560-4326, ext. 30296

Project Description


This project involves the furnishing of all materials, labor, equipment, tools, etc. unless otherwise specified, for the complete removal and installation of sidewalks and curb ramps at various locations throughout the city.

Project Schedule

The following schedule is estimated and may change.
  • Advertisement:  October 16, 2017
  • Pre-Bid Meeting: November 1, 2017
  • Bid Opening: November 15, 2017
  • Anticipated Construction Start Date: Monday, April 9, 2018
    • Old Farm Curb Repair: Complete
    • Fisher Heights Curb Repair: Complete
    • E Weaver Street at Cornwallis Road: Complete
    • Southwest Durham Drive: Complete
    • Chapel Hill Road: Complete
    • #19 and #20 Aly: Complete
    • S Roxboro Street at CC Spaulding: Complete
    • 9th Street: Complete
    • Campus Walk Avenue at Morreene Road: August 2018
    • Lynch Street: August 2018
    • E Carver Street Curb Ramps: September 2018
    • S Roxboro Street Curb Ramps: September 2018
    • E Main Street: October 2018
    • Main Street at Morning Glory Avenue: October 2018
    • Mangum Street: November 2018
    • Cleveland Street: November 2018
    • Archdale Drive: December 2018
    • E Main Street, S Elizabeth Street, Hood Street, E Ramseur Street Curb Ramps: December 2018
  • Anticipated Contract Completion:  Friday, March 30, 2019

Project Status


White Oak Construction is currently working on Campus Walk and Lynch Street.

  • Englewood Street: Complete