Valley Springs Park ADA Improvements

Nia Rodgers, Senior Project Manager
919-560-4197, ext. 21225

Location


Valley Springs Park, 3805 Valley Springs Road Durham, NC 27712 Map


Team Members


Kimley-Horn & Associates

Budget


$788,000 Construction Budget
$881,764 Total Budget

Current Phase


Construction


Expected Completion


Spring 2021

Project Description


The combined project, West Point on the Eno (WPOE) and Valley Springs Park, will address remaining accessibility citations and associated site improvements. At Valley Springs Park the scope of work will include accessible improvements to existing parking areas, pedestrian walkways, and restroom facilities. At WPOE the scope of work will include concept design and a Basis of Design Report for connectivity improvements throughout the historic core of the park and the accessibility of historic amenities.