Project Status


Work began on this contract in September 2017 and is expected to continue through June 2019.  Upcoming and completed project sites are listed below.

Key Project Dates


  • Advertisement: January 20, 2017
  • Pre-Bid Conference: February 3, 2017
  • Bid Opening: February 20, 2017
  • Notice to Proceed: July 28, 2017

Project Description


The project includes the furnishing of all materials, labor, equipment, tools, etc. unless otherwise specified, for the complete inspection of portions of the MS4 for specified site locations throughout the City of Durham. Inspections of the MS4 will include location and verification of system components, inspections to locate possible illicit discharges into the system, and general inspections of system components to document condition.

​Outstanding Project Sites


  • Alpine Road
  • Crest Street Park
  • Elmira Avenue Park
  • Liberty Street 
  • North Plum Street
  • Williams Water Treatment Plant
  • Willowdale Drive 

​Completed Project Sites


  • Alton Street and Wayne Circle
  • Bacon Street
  • Capps Street 
  • Angier Avenue 
  • West Lavender Street 
  • Wrightwood Park
  • Shady Oaks Park
  • C. M. Herndon Park 
  • Oval Drive Park