This project involves the furnishing of all materials, labor, equipment, tools, etc. unless otherwise specified, for the complete installation of 11 speed humps in various locations around the city. 


Project Schedule


  • Advertisement - January 30, 2017
  • Pre-Bid Meeting - February 14, 2017 
  • Bid Opening - March 1, 2017 
  • Project Completion - June 2017

Project Status


This project has been completed by Asphalt Experts.