ST-264 Fayetteville Road Improvements

Project Manager


Ed Venable, PE
Email
Phone: 919-560-4326, ext. 30233

Project Description


The City is moving towards construction of project ST-264, Fayetteville Road Improvements.
The project has been updated to incorporate the former ST-254 Fayetteville/Buxton/Riddle Realignment Project, in order to more effectively utilize the City's resources and provide a more coordinated and less disruptive construction process.  

The Fayetteville Road Improvements Project will consist of widening and enhancing Fayetteville Road from Barbee Road to Cornwallis Road.  The Fayetteville/Buxton/Riddle Road Realignment Project consists of converting the junction of Buxton and Riddle Roads to a traditional intersection.  We are excited about this work and hope it will provide a welcomed improvement to the neighborhood and the traveling community. 

​Project Schedule


The anticipated completion of this project is Fall 2020.  However, the contractor is entitled to rain delays; when it is too wet to work; and those days are added into the completion time.  This is an estimated date of completion, since the weather conditions impact the project schedule.

The Notice to Proceed date was March 4, 2019.  The contractor has 530 calendar days to substantially complete the project and upon NTP the estimated completion date was August 15, 2020.  


Project Status


Construction is underway & is scheduled to be complete in Fall 2020.  This is a City funded project.

**IMPORTANT:  There is a significant detour coming up for those who use Barbee Road.  The Barbee Road closure is slated begin on 10/19/19 and last for 28 calendar days.  Typically, traffic will be affected between 9:00 a.m. and 4:00 p.m. due to lane closures required to complete the work. 

Below is a diagram of the ATT Detour at Solite Park for pedestrians and bicyclists along with the Barbee Road Detour.

ATT Detour through Solite Park, Page 1
ATT Detour Through Solite Park Sept 2019_Page_2
Barbee Road Detour

Advertisement Info.

5/28/2018: This project is currently available for bid as described in documents at right.

6/22/2018: Due to a lack of participation at the pre-bid meeting on June 19, this project is hereby re-advertised as of this date as described in documents at right.

Key dates:

Contract AdvertisementFriday, June 22, 2018
Mandatory Pre-Bid MeetingWednesday, July 11, 2018
Bid OpeningTuesday, July 24, 2018
Notice to ProceedThursday, November 15, 2018
Project CompletionMonday, December 30, 2019

7/12/2018:  Please note the addition of the Pre-Bid meeting minutes at right, along with the attendance sheet.  The attendees listed are the only prime contractors from whom the City will accept a bid.

7/24/2018: Please note the addition of Addendum 1 at right. Note also that the bid opening date has been extended to August 14, 2018.

8/8/2018: Please note the addition of Addendum 2 at right.

8/17/2018: Please note the addition of Addendum 3 at right. The project is hereby re-advertised as of this date as described in documents at right.

Contract AdvertisementFriday, August 17, 2018
Pre-Bid MeetingTuesday, September 04, 2018
Bid OpeningFriday, September 21, 2018

9/11/2018: Please note the addition of Addenda 4-6 at right. Bid opening is postponed until 3:00 PM on September 21, 2018, due to inclement weather.