News Flash

Durham Central Park Waterline Replacement Project Updates

Posted on: August 11, 2017

Project Update | August 11, 2017

Central Park Waterline Replacement Project Update and Two-Week Look Ahead

August 11, 2017

The City appreciates your ongoing patience with the work along the busy corridors associated with the Central Park Waterline Replacement Project. Additional information regarding this project can be found at: http://durhamnc.gov/1251/Durham-Central-Park-Waterline-Replacemen.

Planned Road / Lane Closures will occur as follows:

  • Week of 8/14:
    • Corporation Street westbound will be closed between Liggett Street and North Duke Street.
    • Eastbound Lane of Fernway Avenue will be closed between Morris Street and Fuller Street.
  • Week of 8/21:
    • Corporation Street westbound will be closed between Liggett Street and North Duke Street.
    • Eastbound Lane of Fernway Avenue will be closed between Morris Street and Fuller Street.
    • Fuller Street will be closed between Corporation Street and Fernway Avenue.

Week of August 14, 2017: 

  • Corporation Street will be reduced to one lane as water line installation begins.
    • Traffic control signs and markings will be used for all traffic detours.
    • Flaggers will be utilized for traffic control as needed.
    • Sidewalk traffic will be disrupted.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • On-street parking will be closed in work areas.
    • Planned work hours are 7 AM to 6 PM.
    • No water or sewer service disruptions are anticipated.
  • Fernway Avenue will be reduced to one lane as water line installation begins.
    • Traffic control signs and markings will be used for all traffic detours.
    • Flaggers will be utilized for traffic control as needed.
    • Sidewalk traffic will be disrupted.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • On-street parking will be closed in work areas.
    • Planned work hours are 7 AM to 6 PM.
    • No water service disruption is anticipated.
  • Line testing will occur on Fernway Avenue from Morris Street to Fuller Street and then on Fuller Street from Fernway Avenue to W. Corporation Street.

Saturday - Sunday August 19-20, 2017:

  • No work planned. Fernway Avenue will be reduced to one lane between Fuller Street and Morris Street. W. Corporation Street westbound lane will be closed between Liggett Street and N. Duke Street.

 Week of August 21, 2017: 

  • Corporation Street will be reduced to one lane as water line installation continues.
    • Traffic control signs and markings will be used for all traffic detours.
    • Flaggers will be utilized for traffic control as needed.
    • Sidewalk traffic will be disrupted.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • On-street parking will be closed in work areas.
    • Planned work hours are 7 AM to 6 PM.
    • No water or sewer service disruptions are anticipated.
  • Fernway Avenue will be reduced to one lane as water line installation continues.
    • Traffic control signs and markings will be used for all traffic detours.
    • Flaggers will be utilized for traffic control as needed.
    • Sidewalk traffic will be disrupted.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • On-street parking will be closed in work areas.
    • Planned work hours are 7 AM to 6 PM.
    • Water service disruptions are anticipated. Residents and business owners will be contacted seven days prior to disruption.
  • Fuller Street will be closed as water and sewer line installation continues.
    • Traffic control signs and markings will be used for all traffic detours.
    • Flaggers will be utilized for traffic control as needed.
    • Sidewalk traffic will be disrupted.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • On-street parking will be closed in work areas.
    • Planned work hours are 7 AM to 6 PM.
    • Water service disruptions are anticipated. Residents and business owners will be contacted seven days prior to disruption.

Saturday - Sunday August 26-27, 2017:

  • No work planned. Fernway Avenue will be reduced to one lane between Fuller Street and Morris Street. Fuller Street will be closed between Corporation Street and Fernway Avenue. W. Corporation Street westbound lane will be closed between Liggett Street and N. Duke Street.

Additional information regarding this work can be found at www.DurhamOperationGreenlight.org. Find more information about all of the department’s current projects at www.DurhamWaterProjects.org. If you have questions, please email DowntownLoopWRP@DurhamNC.gov.

Facebook Twitter Google Plus Email

Other News in Durham Central Park Waterline Replacement Project Updates

Project Update | June 14, 2018

Posted on: June 14, 2018

Project Update | June 7, 2018

Posted on: June 7, 2018

Project Update | May 31, 2018

Posted on: May 31, 2018

Project Update | May 31, 2018

Posted on: May 31, 2018

Project Update | May 24, 2018

Posted on: May 24, 2018

Project Update | May 18, 2018

Posted on: May 18, 2018

Project Update | May 10, 2018

Posted on: May 10, 2018

Project Update | May 3, 2018

Posted on: May 3, 2018

Project Update | April 26, 2018

Posted on: April 26, 2018

Project Update | April 19, 2018

Posted on: April 19, 2018

Project Update | April 12, 2018

Posted on: April 12, 2018

Project Update | April 5, 2018

Posted on: April 5, 2018

Project Update | March 29, 2018

Posted on: March 29, 2018

Project Update | March 23, 2018

Posted on: March 23, 2018

Project Update | March 16, 2018

Posted on: March 16, 2018

Project Update | March 8, 2018

Posted on: March 8, 2018

Project Update | March 1, 2018

Posted on: March 1, 2018

Project Update | February 22, 2018

Posted on: February 22, 2018

Project Update | February 15, 2018

Posted on: February 15, 2018

Project Update | February 9, 2018

Posted on: February 9, 2018

Project Update | February 1, 2018

Posted on: February 1, 2018

Project Update | January 25, 2018

Posted on: January 25, 2018

Project Update | January 19, 2018

Posted on: January 19, 2018

Project Update | January 12, 2018

Posted on: January 12, 2018

Project Update | January 4, 2018

Posted on: January 4, 2018

Project Update | December 29, 2017

Posted on: December 29, 2017

Project Update | December 21, 2017

Posted on: December 21, 2017

Project Update | December 14, 2017

Posted on: December 14, 2017

Project Update | December 7, 2017

Posted on: December 7, 2017

Project Update | December 1, 2017

Posted on: December 1, 2017

Project Update | November 17, 2017

Posted on: November 17, 2017

Project Update | November 9, 2017

Posted on: November 9, 2017

Project Update | November 2, 2017

Posted on: November 2, 2017

Project Update | October 19, 2017

Posted on: October 19, 2017

Project Update | October 13, 2017

Posted on: October 13, 2017

Project Update | October 5, 2017

Posted on: October 5, 2017

Project Update | September 28, 2017

Posted on: September 28, 2017

Project Update | September 21, 2017

Posted on: September 21, 2017

Project Update | September 14, 2017

Posted on: September 14, 2017

Project Update | September 8, 2017

Posted on: September 8, 2017

Project Update | August 31, 2017

Posted on: August 31, 2017

Project Update | August 25, 2017

Posted on: August 25, 2017

Project Update | August 18, 2017

Posted on: August 18, 2017

Project Update | August 4, 2017

Posted on: August 4, 2017

Project Update | July 28, 2017

Posted on: July 28, 2017

Project Update | July 21, 2017

Posted on: July 21, 2017

Project Update | July 14, 2017

Posted on: July 14, 2017

Project Update | July 7, 2017

Posted on: July 7, 2017

Project Update | June 29, 2017

Posted on: June 29, 2017