East Main Street Waterline Replacement Project Updates

Posted on: July 20, 2017

Project Update | July 20, 2017

East Main Street Waterline Replacement Project Update and Two-Week Look Ahead

July 20, 2017

Improvements to the City’s waterline infrastructure will continue along the East Main Street corridor. Additional information regarding this project can be found at: http://durhamnc.gov/3001/East-Main-Street-Waterline-Replacement.

 

Planned Road / Lane Closures will occur as follows:

  • Week of 7/24:
    • Lane shifts and flaggers on East Main Street between Church Street and Fayetteville Street, Hood Street, and South Elizabeth Street.
    • Lane closures on Ramseur Street between Dillard Street and Fayetteville Street.
    • Lane closure on East Main Street between Church and Roxboro streets during weekend work.
  • Week of 7/31:
    • Lane shifts and flaggers on East Main Street between Roxboro Street and Fayetteville Street, Hood Street, and South Elizabeth Street.
    • Lane closures on Ramseur Street between Dillard Street and Fayetteville Street.

Saturday-Sunday July 22-23, 2017:

  • No work is planned for Saturday, July 22nd or Sunday, July 23rd.

Week of July 24, 2017: 

  • Restoration of sidewalks, curb, etc. and abandonment of existing waterlines in East Main Street between Roxboro and Fayetteville streets, Hood Street, South Elizabeth Street, and Ramseur Street will continue.
    • Lane shifts and flaggers will be used to maintain traffic at isolated locations in the project area.
    • Through traffic on East Main Street will be maintained.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Pedestrian and driveway access to buildings / facilities will be maintained at all times.
  • Stormwater installation will begin on East Main Street between S. Elizabeth / Commerce and Hood streets.
    • Lane closures and detours will be used to maintain traffic at stormwater crossing locations on East Main Street.
    • Through traffic on East Main Street will be maintained.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Pedestrian and driveway access to buildings / facilities will be maintained at all times.
  • Stormwater installation along Ramseur Street between Dillard and Hood streets will continue.
    • Lane closures and detours will be used to maintain traffic at stormwater crossing locations at Hood and S. Elizabeth streets.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Pedestrian and driveway access to buildings / facilities will be maintained at all times.
  • Existing stamped concrete in East Main Street on the west side of Roxboro Street will be removed.
    • Lane closures and shifts will be used to maintain traffic in both directions during work.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Pedestrian and driveway access to buildings / facilities will be maintained at all times.

Friday - Monday July 28-31, 2017:

  • Stamped concrete restoration will take place on East Main Street on the west side of Roxboro Street.
    • East Main Street will be closed between Church Street and Roxboro Street from 7 PM on Friday through 6 AM on Monday.
    • Traffic control signs and markings will be used for East Main Street detours.
    • Noise levels in excess of the current City noise ordinance are anticipated on Friday evening and Saturday morning.
    • Pedestrian and driveway access to buildings / facilities will be maintained at all times.

Week of July 31, 2017: 

  • Restoration of sidewalks, curb, etc. and abandonment of existing waterlines in East Main Street between Roxboro and Fayetteville streets, Hood Street, South Elizabeth Street, and Ramseur Street will continue.
    • Lane shifts and flaggers will be used to maintain traffic at isolated locations in the project area.
    • Through traffic on East Main Street will be maintained.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Pedestrian and driveway access to buildings / facilities will be maintained at all times.
  • Stormwater installation will continue on East Main Street between Elizabeth and Hood streets.
    • Lane closures and detours will be used to maintain traffic at stormwater crossing locations on East Main Street.
    • Through traffic on East Main Street will be maintained.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Pedestrian and driveway access to buildings / facilities will be maintained at all times.
  • Stormwater installation along Ramseur Street between Dillard and Hood streets will continue.
    • Lane closures and detours will be used to maintain traffic at stormwater crossing locations at Hood and S. Elizabeth streets.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Pedestrian and driveway access to buildings / facilities will be maintained at all times.

Saturday-Sunday August 5-6, 2017:

  • No work is planned for Saturday, August 5th or Sunday, August 6th.

Future Weeks:

  • Restoration of sidewalks and other surfaces impacted by the project will continue.
  • Waterline service reconnections in Angier Avenue between East Main Street and Elm Avenue will coordinated with affected residents. A lane closure on Angier Avenue will be required to complete the work.
  • Stormwater improvements along East Main Street will continue.
  • Pavement improvements in the intersection of Fayetteville / East Main street are anticipated to occur in late August. An intersection closure with traffic detours is planned for approximately 4-5 days to complete the work.
  • Work will exceed the current City noise ordinance.
  • Additional information regarding this work can be found at www.DurhamOperationGreenlight.org. Find more information about all of the department’s current projects at www.DurhamWaterProjects.org. If you have questions, please email DowntownLoopWRP@DurhamNC.gov.

Facebook Twitter Google Plus Email

Other News in East Main Street Waterline Replacement Project Updates

Project Update | October 12, 2017

Posted on: October 12, 2017

Project Update | October 5, 2017

Posted on: October 5, 2017

Project Update | September 28, 2017

Posted on: September 28, 2017

Project Update | September 21, 2017

Posted on: September 21, 2017

Project Update | September 14, 2017

Posted on: September 14, 2017

Project Update | September 7, 2017

Posted on: September 7, 2017

Project Update | August 31, 2017

Posted on: August 31, 2017

Project Update | August 24, 2017

Posted on: August 24, 2017
E Main and Fayetteville Detour 8.18-8.21

Project Update | August 17, 2017

Posted on: August 17, 2017