Project Update | June 22, 2017

East Main Street Waterline Replacement Project Update and Two-Week Look Ahead

June 22, 2017

Improvements to the City’s waterline infrastructure will continue along the East Main Street corridor. Additional information regarding this project can be found at: http://durhamnc.gov/3001/East-Main-Street-Waterline-Replacement.

 

Planned Road / Lane Closures will occur as follows:

  • Week of 6/26:
    • Lane shifts and flaggers on East Main Street between Dillard Street and Fayetteville Street.
    • Lane closures on Ramseur Street between Hood Street and Fayetteville Street.
  • Week of 7/3:
    • Lane shifts and flaggers on East Main Street between Roxboro Street and Fayetteville Street.
    • Lane closures on Ramseur Street between Dillard Street and Fayetteville Street.

Saturday-Sunday June 24-25, 2017:

  • No work is planned.

Week of June 26, 2017: 

  • Final waterline and service connections on East Main Street between Dillard and Fayetteville streets will continue.
    • Work includes final waterline connections at Dillard / East Main streets.
    • Lane shifts and flaggers will be used to maintain traffic at installation locations on East Main Street.
    • Waterline service reconnections will be coordinated with affected parties at least seven days in advance of interruption.
    • Through traffic on East Main Street will be maintained.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Pedestrian and driveway access to buildings / facilities will be maintained at all times.
  • Waterline and service installations along Ramseur Street between Hood and Fayetteville streets will continue.
    • Lane shifts and flaggers will be used to maintain traffic at waterline crossing locations.
    • Waterline service reconnections will be coordinated with affected parties at least seven days in advance of interruption.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Pedestrian and driveway access to buildings / facilities will be maintained at all times.

Saturday-Sunday July 1-2, 2017:

  • Waterline abandonment on East Main Street between Roxboro and Fayetteville streets will continue.
    • Lane shifts and flaggers will be used to maintain traffic at installation locations on East Main Street.
    • Through traffic on East Main Street will be maintained.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Pedestrian and driveway access to buildings / facilities will be maintained at all times.

Week of July 3, 2017: 

  • No work will take place on July 4th.
  • Existing waterline abandonment on East Main Street between Roxboro and Fayetteville streets will take place.
    • Isolated lane shifts and flaggers will be used to maintain traffic at abandonment locations on East Main Street.
    • Through traffic on East Main Street will be maintained.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Pedestrian and driveway access to buildings / facilities will be maintained at all times.
  • Waterline and service installations along Ramseur Street between Hood and Fayetteville streets will continue.
    • Lane shifts and flaggers will be used to maintain traffic at waterline crossing locations.
    • Waterline service reconnections will be coordinated with affected parties at least seven days in advance of interruption.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Pedestrian and driveway access to buildings / facilities will be maintained at all times.
  • Stormwater installation along Ramseur Street between Dillard and Hood streets will continue.
    • Lane closures and detours will be used to maintain traffic at stormwater crossing locations at Hood and S. Elizabeth streets.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Pedestrian and driveway access to buildings / facilities will be maintained at all times.

Saturday-Sunday July 8-9, 2017:

  • Waterline abandonment on East Main Street between Roxboro and Fayetteville streets will continue.
    • Lane shifts and flaggers will be used to maintain traffic at installation locations on East Main Street.
    • Through traffic on East Main Street will be maintained.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Pedestrian and driveway access to buildings / facilities will be maintained at all times.

Future Weeks:

  • Restoration of sidewalks and other surfaces impacted by the project will continue.
  • Waterline service reconnections in Angier Avenue between East Main Street and Elm Avenue will coordinated with affected residents.
  • Stormwater improvements along East Main Street will continue.
  • Pavement improvements in the intersection of Fayetteville / East Main street are anticipated to occur in late July. An intersection closure with traffic detours is planned for approximately 4-5 days to complete the work.
  • Work will exceed the current City noise ordinance.
  • Additional information regarding this work can be found at www.DurhamOperationGreenlight.org. Find more information about all of the department’s current projects at www.DurhamWaterProjects.org. If you have questions, please email DowntownLoopWRP@DurhamNC.gov.

Facebook Twitter Google Plus Email

Other News in East Main Street Waterline Replacement Project Updates

Project Update | October 12, 2017

Posted on: October 12, 2017

Project Update | October 5, 2017

Posted on: October 5, 2017

Project Update | September 28, 2017

Posted on: September 28, 2017

Project Update | September 21, 2017

Posted on: September 21, 2017

Project Update | September 14, 2017

Posted on: September 14, 2017

Project Update | September 7, 2017

Posted on: September 7, 2017

Project Update | August 31, 2017

Posted on: August 31, 2017

Project Update | August 24, 2017

Posted on: August 24, 2017
E Main and Fayetteville Detour 8.18-8.21

Project Update | August 17, 2017

Posted on: August 17, 2017

Project Update | August 10, 2017

Posted on: August 10, 2017

Project Update | August 3, 2017

Posted on: August 3, 2017

Project Update | July 27, 2017

Posted on: July 27, 2017

Project Update | July 20, 2017

Posted on: July 20, 2017

Project Update | July 13, 2017

Posted on: July 13, 2017

Project Update | July 6, 2017

Posted on: July 6, 2017

Project Update | June 29, 2017

Posted on: June 29, 2017