East Main Street Waterline Replacement Project Updates

Posted on: October 5, 2017

Project Update | October 5, 2017

East Main Street Waterline Replacement Project Update and Two-Week Look Ahead

October 5, 2017

We are nearing the end! Improvements to the City’s waterline infrastructure will continue along the East Main Street corridor. Additional information regarding this project can be found at: http://durhamnc.gov/3001/East-Main-Street-Waterline-Replacement.

Planned Road / Lane Closures will occur as follows:

  • Week of 10/9:
    • Lane shifts and flaggers on East Main Street between Roxboro Street and Fayetteville Street, Hood Street, South Elizabeth Street, and Ramseur Street.
  • Week of 10/16:
    • Lane shifts and flaggers on East Main Street between Roxboro Street and Fayetteville Street, Hood Street, South Elizabeth Street, and Ramseur Street.

Saturday-Sunday October 7-8, 2017:

  • No work is planned for Saturday, October 7th or Sunday, October 8th.

Week of October 9, 2017: 

  • Sidewalk/curb replacements and abandonment of existing waterlines in East Main Street between Roxboro and Fayetteville streets, Hood Street, South Elizabeth Street, and Ramseur Street will continue.
    • Lane shifts and flaggers will be used to maintain traffic at isolated locations in the project area.
    • Through traffic on East Main Street will be maintained.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Pedestrian and driveway access to buildings / facilities will be maintained at all times.

Saturday-Sunday October 14-15, 2017:

  • No work is planned for Saturday, October 14th or Sunday, October 15th.

Week of October 16, 2017: 

  • Sidewalk/curb replacements and abandonment of existing waterlines in East Main Street between Roxboro and Fayetteville streets, Hood Street, South Elizabeth Street, and Ramseur Street will continue.
    • Lane shifts and flaggers will be used to maintain traffic at isolated locations in the project area.
    • Through traffic on East Main Street will be maintained.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Pedestrian and driveway access to buildings / facilities will be maintained at all times.

Future Weeks:

Facebook Twitter Google Plus Email

Other News in East Main Street Waterline Replacement Project Updates

Project Update | October 12, 2017

Posted on: October 12, 2017

Project Update | September 28, 2017

Posted on: September 28, 2017

Project Update | September 21, 2017

Posted on: September 21, 2017

Project Update | September 14, 2017

Posted on: September 14, 2017

Project Update | September 7, 2017

Posted on: September 7, 2017

Project Update | August 31, 2017

Posted on: August 31, 2017

Project Update | August 24, 2017

Posted on: August 24, 2017
E Main and Fayetteville Detour 8.18-8.21

Project Update | August 17, 2017

Posted on: August 17, 2017

Project Update | August 10, 2017

Posted on: August 10, 2017

Project Update | August 3, 2017

Posted on: August 3, 2017

Project Update | July 27, 2017

Posted on: July 27, 2017

Project Update | July 20, 2017

Posted on: July 20, 2017

Project Update | July 13, 2017

Posted on: July 13, 2017

Project Update | July 6, 2017

Posted on: July 6, 2017

Project Update | June 29, 2017

Posted on: June 29, 2017

Project Update | June 22, 2017

Posted on: June 22, 2017