2013 Stormwater Infrastructure Repairs (SD-2013-01)

Project Manager
Dana Hornkohl, PE
Email
Phone: 919-560-4326, ext. 30246

Project Status
White Oak Construction Corporation is performing construction under this contract.  Currently, the
project is on schedule.

Key Project Dates
  • Notice to Proceed: January 8, 2014
Project Description
The project involves the furnishing of all materials, labor, equipment, tools, etc. unless otherwise specified, for the complete installation of repairs, rehabilitation, and improvements of stormwater drainage systems at various site locations throughout the City of Durham. Status of the projects at these locations is shown below.

Completed Project Sites
  • 603 Brookwood Drive
  • 210 & 212 Edward Street
  • 2018 Woodrow Street
  • Ashe Street and Owen Street Drainage Improvements
  • Campus Hills Park Lake Dewatering
  • Clermont Road Culvert Replacement
  • East Ellerbe Street at Stephenson Street Intersection Improvements
  • East Main Street Pipe Replacement
  • Friendship Road Pipe Replacement
  • Gentry Drive Driveway Pipe Replacement
  • Goodyear Circle Drainage Improvements
  • Long Meadow Park Pool Pipe Replacement
  • Maplewood Cemetery 1 Drainage Imp. (Pauli Murray House)
  • Maplewood Cemetery 2 Pipe Replacement
  • Maplewood Cemetery 3 Pipe Replacement
  • Maplewood Cemetery 4 Pipe Replacement
  • Maplewood Cemetery 5 Drainage Imp.
  • Maplewood Cemetery 6 Pipe Replacement
  • Maplewood Cemetery 7 Pipe Replacement
  • Otis Street at Formosa Street at Concord Street Intersection Imp.
  • Pineview Road Pipe Replacement
  • Red Maple Park Pipe Replacement
  • Rocky Creek Stream Restoration
  • Shoccoree Drive Dam Improvements
  • Third Fork Creek Temporary Stream Bank Stabilization 2
  • Twin Lakes Park Emergency Pipe Replacement
  • Watts Street Pipe Replacement No. 1
  • West Lakewood Avenue Sidewalk
  • West Markham Avenue at Onslow Street Intersection Improvements
Pending Project Sites
  • 3315 Fayetteville Street
  • Corcoran Street Parking Lot Pipe Replacement
  • Leonard Drive Pipe Replacement
  • Pinecrest Road Drainage Improvements
  • Wortham Avenue Drainage Improvements