2017 Ravenstone and Stone Hill Estates Paving Project (ST-278)

Project Manager


Kitty M. Thomas, EI
Phone: 919-560-4326, ext. 30218

Project Description


This project involves the furnishing of all materials, labor, equipment, tools, etc. unless otherwise specified, for the repair and final paving of various streets in Ravenstone and Stone Hill Estates subdivisions as well as micro-surfacing of various streets in or near these subdivisions in the City of Durham.

Project Schedule

  • Advertisement: November 9, 2016
  • Pre-Bid Meeting: November 17, 2016 at 11 a.m.
  • Bid Opening: December 8, 2016 at 10 a.m.   *Apparent Low Bidder: Fred Smith Co.*
  • Meeting with residents of Ravenstone subdivision:  April 17, 2017 at 6 p.m. at the East Regional Library
  • Meeting with residents of Stone Hill Estates subdivision :  April 24, 2017 at 6:15 p.m. at Southern High School Media Center
  • Anticipated Construction Start in Ravenstone

     

    subdivision

    :  May 2017


  • Anticipated Construction Start in Stone Hill Estates subdivision: Late June 2017
  • Anticipated Construction Completion: September 2017

Project Status/Update

Construction phase underway. 1st lift asphalt paving in Ravenstone subdivision has been completed. Final paving of these streets will be completed in early June 2017. Work in Stone Hill Estates Subdivision is scheduled to start by mid June 2017.

Construction Phase Updates

  • 1st lift asphalt paving in Ravenstone subdivision was completed on May 19, 2017
  • Milling, patching and 1st lift asphalt paving was completed on Oakchest Ct, Ashburn Ln, Rondelay Dr, Conover Rd, Weathervane Dr, Spicewood Ct, Red Sage Ct, Hillview Dr and English Ivy Dr

Upcoming Work Schedule

  • Any required adjustment/ replacement of Manholes and water valves frames and covers in Ravenstone subdivision will be identified and completed in the upcoming weeks.