2017 Ravenstone and Stone Hill Estates Paving Project (ST-278)

Project Manager


Kitty M. Thomas, EI
Phone: 919-560-4326, ext. 30218

Project Description


This project involves the furnishing of all materials, labor, equipment, tools, etc. unless otherwise specified, for the repair and final paving of various streets in Ravenstone and Stone Hill Estates subdivisions as well as micro-surfacing of various streets in or near these subdivisions in the City of Durham.

Project Schedule

  • Advertisement: November 9, 2016
  • Pre-Bid Meeting: November 17, 2016 at 11 a.m.
  • Bid Opening: December 8, 2016 at 10 a.m.   *Apparent Low Bidder: Fred Smith Co.*
  • Meeting with residents of Ravenstone subdivision:  April 17, 2017 at 6 p.m. at the East Regional Library
  • Meeting with residents of Stone Hill Estates subdivision :  April 24, 2017 at 6:15 p.m. at Southern High School Media Center
  • Second meeting with residents of Stone Hill Estates subdivision:  June 5, 2017 at 7:15 p.m. at the East Regional Library
  • Construction Start in Ravenstone

     

    subdivision

    :  May 10, 2017


  • Anticipated Construction Start in Stone Hill Estates subdivision: June 26, 2017
  • Anticipated Construction Completion: September 2017

Project Status/Update

Construction phase underway. 1st lift asphalt paving and utility adjustments in Ravenstone subdivision has been completed. Final paving of these streets started on June 12, 2017. Work in Stone Hill Estates Subdivision is scheduled to start in June 2017.

Construction Phase Updates

  • Final lift asphalt paving in Ravenstone subdivision started on June 12, 2017.
  • Manhole/watervalve adjustments/replacements in Ravenstone subdivision were completed on June 1, 2017

Upcoming Work Schedule

  • Final lift asphalt paving in Ravenstone started on June 12, 2017 and is anticipated to be completed by June 16, 2017.
  • Streets Scheduled to be paved this week of June 12, 2017: Ashburn Ln, English Ivy Dr, Hillview Dr, Rondelay Dr, Conover Rd, Spicewood Ct, Red Sage Ct, Oakchest Ct and
    Weathervane Dr
  • Work in Stone Hill Estates subdivision is scheduled to start on June 26, 2017.