2017 Ravenstone and Stone Hill Estates Paving Project (ST-278)

Project Manager


Kitty M. Thomas, EI
Phone: 919-560-4326, ext. 30218

Project Description


This project involves the furnishing of all materials, labor, equipment, tools, etc. unless otherwise specified, for the repair and final paving of various streets in Ravenstone and Stone Hill Estates subdivisions as well as micro-surfacing of various streets in or near these subdivisions in the City of Durham.

Project Schedule

  • Advertisement: November 9, 2016
  • Pre-Bid Meeting: November 17, 2016 at 11 a.m.
  • Bid Opening: December 8, 2016 at 10 a.m.   *Apparent Low Bidder: Fred Smith Co.*
  • Meeting with residents of Ravenstone subdivision:  April 17, 2017 at 6 p.m. at the East Regional Library
  • Meeting with residents of Stone Hill Estates subdivision :  April 24, 2017 at 6:15 p.m. at Southern High School Media Center
  • Second meeting with residents of Stone Hill Estates subdivision:  June 5, 2017 at 7:15 p.m. at the East Regional Library
  • Construction Start in Ravenstone

     

    subdivision

    :  May 10, 2017


  • Anticipated Construction Start in Stone Hill Estates subdivision: July 5, 2017
  • Anticipated Construction Completion: September 2017

Project Status/Update

Construction phase underway. Final lift asphalt paving in Ravenstone subdivision has been completed. Work in Stone Hill Estates Subdivision started in July 2017.

Construction Phase Updates

  • Final lift asphalt paving in Ravenstone subdivision was completed on June 15, 2017.
  • Work in Stone Hill Estates subdivision is started on July 5, 2017.

Upcoming Work Schedule

  • Streets Scheduled to be milled and paved(first lift) this week of July 10, 2017: Obsidian Way and Turquoise Dr
  • Patching of streets in the project limits for micro-surfacing in Stone Hill Estates subdivision scheduled to start this week of July 10
  • Week of July 17: Manhole/Water valve adjustments on streets to be paved; Start of final paving of streets in Stone Hill Estates subdivision
*Work schedules are subject to change