2018 Drainage Structure Access and Stabilization (SD-2018-09)​

Project Manager

Dana P Hornkohl, PE
Phone: 919-560-4326, ext. 30246


Project Status


This contract has been awarded to White Oak Construction Corp. of N.C.  Work began in September 2018.

Key Project Dates


  • Advertisement: April 13, 2018
  • Pre-Bid Conference: April 26, 2018
  • Bid Opening: May 15, 2018
  • Notice to Proceed: August 20, 2018

Project Description


The project involves the furnishing of all materials, labor, equipment, tools, etc. unless otherwise
specified, for the complete installation of repairs, rehabilitation, and improvements of stormwater
drainage systems at various site locations throughout the City of Durham.

Outstanding Project Sites


  • American Tobacco Trail
  • C. M. Herndon park
  • Crest Street Park
  • Dakota Street
  • Durham Armory
  • Englewood Avenue
  • Shady Oaks Park
  • Third Fork Creek Trail
  • Wrightwood Avenue
  • Wrightwood Park

​Completed Project Sites

  • Beechwood Cemetery
  • Hillandale Golf Course
  • Technology Drive