This project will include several components. These include short-term construction repairs, solicitation of professional services, and establishment of a long-term asset management plan for bridge structures.
Disadvantaged Business Enterprises
The Disadvantaged Business Enterprise (DBE) goals for this project will vary. Subcontractors must be certified by NCDOT as a DBE in order for their participation to count towards the goal. To find DBEs certified by NCDOT, go to https://partner.ncdot.gov/VendorDirectory/default/html .
Guardrail Repair Project Status
01/29/18: Pre-selected firms are invited to provide quotes to the city for ST-288A, Guardrail Repair.
02/26/18: No quotes were received.This portion of the project will be withdrawn and will be included in the eventual construction contract for outstanding bridge repairs, subsequent to the outcome of the RFQ process.
RFQ for Engineering Services
2/1/18: The City is issuing a RFQ for Engineering Services for the performance of professional services for six (6) bridges in the City. All qualified firms are invited to submit proposals. Please find the RFQ as well as available reports for the various structures at right.
RFQ Schedule:
Last date for receipt of proposals: Friday, March 9, 2018
Conclude Shortlisting: Friday, March 23, 2018
Conclude Contract Negotiations: Friday, April 6, 2018
City Manager and successful candidate sign contract: Monday, June 4, 2018
Notice to Proceed: Tuesday, June 5, 2018
Contract End Date: Monday, June 3, 2019