2018 SCM Renovation and Rehabilitation (SWDR-2018-01)

Project Manager


Shea S. Bolick, PE, PLS, CFM
Phone: 919-560-4326, ext. 30270

Project Status


Notice to proceed was given and project work commenced on May 1, 2018.  The contractor (Backwater Environmental) worked diligently performing improvements on stormwater control measures in Stonehill Estates, at a Public Works salt dome facility, and Ravenstone subdivision.  All work is substantially complete and with full grass vegetation establishment, minor incidental items, as well as final maintenance, the project will be complete.  The original project completion date was October 28, 2018, however this date will be revised due to extra work not in the original scope of the contract, industry hardships, etc.  It is expected that the stormwater facilities for both Stonehill Estates and Ravenstone subdivisions will be turned over to their respective homeowners associations for future operation and maintenance during the middle to end of November 2018.

Key Project Dates


  • Initial Advertisement:  December 20, 2017
  • Pre-Bid Conference:  January 10, 2018
  • Re-Advertisement:  January 29, 2018
  • Bid Opening:  February 12, 2018 at 2:00 PM
  • Notice to Proceed:  May 1, 2018
  • Work Commencement:  May 1, 2018
  • Substantial Completion: October 15, 2018

Project Description


The project involves the furnishing of all materials, labor, equipment, tools, etc., unless otherwise specified, for renovation and rehabilitation activities performed on various stormwater control measures (SCMs) at various site locations throughout the City of Durham.