This project involves the design of sidewalks and bicycle facilities on Hillandale Road from I-85 to NC-147. The total length is 1.1 miles and the design project budget is $457,123. 

The improvements include sidewalks and bicycle facilities.  Functional designs for the project were completed in 2014 and can be accessed using the below link under Functional Designs.  Functional Designs are preliminary designs used for public comment and determining permit needs.  Final designs are now underway and will be added to this web site when available.
 

Project Schedule

  • Anticipated Design Completion:  October 2018
  • Anticipated Right-of-Way Completion:  April 2019
  • Anticipated Bid Advertisement:  January 2020 
  • Anticipated Construction Start:  June 2020
  • Anticipated Construction Completion:  May 2021


Project Status


Ramey Kemp and Associates of Raleigh, NC has been hired as the design firm to prepare plans, obtain permits, and hold informational meetings with stakeholders. They began data collection in July 2017 and currently are in the location and survey phase of the project.