2018 Sidewalk Repairs (SW-62)

Project Manager


Allison Molleson, EI
Phone: 919-560-4326, ext. 30296

Project Description


This project involves the furnishing of all materials, labor, equipment, tools, etc. unless otherwise specified, for the complete removal and installation of sidewalks and curb ramps at various locations throughout the city.

Project Schedule

The following schedule is estimated and may change.
  • Advertisement:  October 16, 2017
  • Pre-Bid Meeting: November 1, 2017
  • Bid Opening: November 15, 2017
  • Anticipated Construction Start Date: Monday, April 9, 2018
    • Old Farm Curb Repair: Complete
    • Fisher Heights Curb Repair: Complete
    • E Weaver Street at Cornwallis Road: Complete
    • Southwest Durham Drive: Complete
    • Chapel Hill Road: Complete
    • #19 and #20 Aly: Complete
    • S Roxboro Street at CC Spaulding: August 2018
    • 9th Street: July 2018
    • Campus Walk Avenue at Morreene Road: August 2018
    • Mangum Street: August 2018
    • Cleveland Street: September 2018
    • E Main Street: September 2018
    • Main Street at Morning Glory Avenue: October 2018
    • Archdale Drive: October 2018
    • Englewood Street: November 2018
    • Lynch Street: December 2018
    • E Carver Street Curb Ramps: January 2019
    • S Roxboro Street Curb Ramps: February 2019
    • E Main Street, S Elizabeth Street, Hood Street, E Ramseur Street Curb Ramps: March 2019
  • Anticipated Contract Completion:  Friday, March 30, 2019

Project Status


White Oak Construction is currently working on Ninth Street Sidewalk.