2018 Sidewalk Repairs (SW-62)

Project Manager


Allison Molleson, EI
Phone: 919-560-4326, ext. 30296

Project Description


This project involves the furnishing of all materials, labor, equipment, tools, etc. unless otherwise specified, for the complete removal and installation of sidewalks and curb ramps at various locations throughout the city.

Project Schedule

The following schedule is estimated and may change.
  • Advertisement:  Monday, October 16, 2017
  • Pre-Bid Meeting:  Wednesday, November 1, 2017
  • Bid Opening:  Wednesday, November 15, 2017
  • Anticipated Construction Start Date: Monday, March 19, 2018
  • Anticipated Contract Completion:  Friday, March 30, 2019

Project Status


Bids were opened on November 15, 2017 at 2:00 p.m. The apparent low bidder is White Oak Construction. The results from the bid opening are as follows:
  • White Oak Construction $1,399,590.00
  • Browe Construction $1,478,135.00
  • JYMCO Construction $1,790,170.00
  • Engineer's Estimate $1,575,052.50