2018 Street Repairs & Repaving (ST-285)

Project Manager


Allison M. Molleson, EIT
Email
Phone: 919-560-4326, ext. 30296

Project Description


This project involves the furnishing of all materials, labor, equipment, tools, etc. unless otherwise specified, for the preservation, repair, and repaving of various streets throughout the City of Durham. 

For information on pavement preservation techniques, see the links on the right. 

Project Schedule


  • Advertisement:  October 16, 2017 
  • Pre-Bid Meeting: November 1, 2017 
  • Bid Opening:  November 15, 2017
  • City Council Approval: January 16, 2018
  • Anticipated Construction Start: May 21, 2018
    • E Main Street: July 5, 2018 - July 27, 2018
    • Hood StreetJuly 5, 2018 - July 27, 2018
    • Ramseur StreetJuly 5, 2018 - July 27, 2018
    • S Elizabeth Street: July 5, 2018 - July 27, 2018
    • S Roxboro Street: June 11, 2018 - July 13, 2018
    • Carver Street: August 2018
    • Fisher Heights Neighborhood: August 2018
    • Old Farm Neighborhood: September 2018
    • Reclamite: October 2018
  • Anticipated Construction Completion:  October 2018

Project Status


Paving operations will begin on May 29 on S Roxboro Street. Fred Smith Company will mill 4 inches of asphalt, adjust utilities and repave 4 inches of asphalt.  

Patching Map: 

http://durhamnc.maps.arcgis.com/apps/View/index.html?appid=ce97988a51544967a4513b578b8ff8c6