2017 Bike+Walk Sidewalk Gaps (SW-64)

Project Manager


Kitty M. Thomas
Phone: 919-560-4326, ext. 30218
Email

Project Description


This project involves the furnishing of all materials, labor, equipment, tools, etc. unless otherwise specified, for the complete installation of sidewalk and curb ramps as required to close sidewalk gaps in various locations in the City of Durham.

Project Schedule

The following schedule is estimated and may change.
  • Advertisement:  Monday, August 1, 2017
  • Pre-Bid Meeting:  Wednesday, August 9, 2017
  • Bid Opening:  Wednesday, August 30, 2017
  • Construction Start: Monday, January 31, 2018

Project Status


Work on Gregson St location started on Friday, February 9, 2018. Work on Green St started on Monday, February 5, 2018. Construction started on January 31, 2018 in Enterprise St. This contract was awarded to Lanier Construction Co. Morehead Avenue and Picket Rd were removed from the project locations.
Upcoming work for Week of February 13, 2018: Concrete Sidewalk Installation on Enterprise St, Green St and Gregson St locations; Work start in Fayetteville St location.