2017 Stormwater Infrastructure Repairs (SD-2017-04)

Project Manager


Yi Wang, PE
Phone: 919-560-4326, ext. 30244

Project Status


Work began on this contract in December 2017 and is expected to be complete in March 2018.  White Oak Construction Corporation of North Carolina is the contractor.

Key Project Dates


  • Advertisements: April 17, 2017 and May 22, 2017. 
  • Pre-Bid Conference: April 26, 2017.
  • Bid Opening: May 18, 2017 and June 6, 2017.
  • Re-Advertisement: August 18, 2017.
  • Second Pre-Bid Conference: August 29, 2017. 
  • Bid Opening: September 19, 2017.
  • Notice to Proceed: December 1, 2017.

Project Description


The project involves the furnishing of all materials, labor, equipment, tools, etc. unless otherwise specified, for the complete installation of repairs, rehabilitation, and improvements of stormwater drainage systems at various site locations throughout the City of Durham.

Project Sites

  • Winburn Avenue Pipe Replacement
  • Unity Village Park Pipe Replacement