2017 MS4 Inspections (SD-2017-03)​

Project Manager


Yi Wang, PE
Phone: 919-560-4326, ext. 30244

Project Status


This contract has been awarded to Prism Contractors, Inc.  Work is expected to continue through June 2019.  Outstanding and completed project sites are listed below.

Key Project Dates


  • Advertisement: January 20, 2017
  • Pre-Bid Conference: February 3, 2017
  • Bid Opening: February 20, 2017
  • Notice to Proceed: July 28, 2017

Project Description


The project includes the furnishing of all materials, labor, equipment, tools, etc. unless otherwise specified, for the complete inspection of portions of the MS4 for specified site locations throughout the City of Durham. Inspections of the MS4 will include location and verification of system components, inspections to locate possible illicit discharges into the system, and general inspections of system components to document condition.

​Outstanding Project Sites


  • Crest Street Park
  • Ottawa Avenue and North Queen Street
  • Sidewalk Bicycle Facilities
  • Williams Water Treatment Plant 

​Completed Project Sites


  • Alpine Road
  • Alton Street and Wayne Circle
  • Angier Avenue
  • Bacon Street
  • Capps Street
  • Clarendon Street
  • C. M. Herndon Park
  • Cobblestone Place
  • Dowd Street
  • Elmira Avenue Park
  • Evergreen Street
  • Gilbert Street
  • Glendale Avenue
  • Liberty Street
  • North Plum Street
  • Oval Drive Park
  • Owen Street
  • Park Avenue
  • Shady Oaks Park
  • South Roxboro Street
  • Starlight Drive
  • West Lavender Avenue
  • Willowdale Drive
  • Wrightwood Park
Similar Contracts: SD-2012-04 & SD-2014-01.