2016 Third Fork Creek Stream Restoration (SD-2016-03)​

Project Manager


Dana P Hornkohl, PE
Phone: 919-560-4326, ext. 30246

Project Site Map



Project Schedule

(Updated March 30, 2017)

Trail Closures


Brief trail closures may be expected during construction of the stream restoration.  The contractor will provide an alternative route for these closures.

The trail will be closed for a period of time while two sections of asphalt trail are replaced with boardwalk.  Public notice will be given in advance of this closure.

Project Status


Construction began on March 20, 2017 with contractor mobilization.  The contractor is Carolina Environmental Contracting, Inc.
 

Key Project Dates


  • Initial Advertisement: June 20, 2016
  • Initial Bid Opening: July 21, 2016
  • Re-Advertisement: August 29, 2016
  • Bid Opening: October 12, 2016
  • Notice to Proceed: March 20, 2017

Project Description


The project includes the furnishing of all materials, labor, equipment, tools, etc. unless otherwise specified, for the stream restoration of Third Fork Creek and new trail boardwalk between Martin Luther King, Jr. Parkway and Cardinal Drive.