2015 East Main Street Culvert Stabilization (SD-2015-01)​

Project Manager
Dana P Hornkohl, PE
Email
Phone: 919-560-4326, ext. *30246

Project Status
This project is complete.

East Main Street between North Maple Street and North Driver Street was closed from February 1st to April 22nd of 2016.  See the DETOUR PLAN for additional temporary traffic patterns.

Key Project Dates
  • Initial Advertisement: May 29, 2015
  • Initial Pre-Bid Conference: June 15, 2015
  • Initial Bid Opening: July 6, 2015
  • Re-Advertisement: July 27, 2015
  • Pre-Bid Conference: August 12, 2015
  • Bid Opening: August 27, 2015
  • Notice to Proceed: January 13, 2016
  • Construction Begins: February 1, 2016
  • Notice of Final Completion: April 12, 2016
Project Description
The project includes the furnishing of all materials, labor, equipment, tools, etc. unless otherwise specified, for the complete stabilization of the East Main Street culvert by means of void filling and soil stabilization using a high density polyurethane system.

Similar Contract: SD-2012-03.