Durham Operation Green Light

Learn about the progress of major transportation and facility projects that may affect travel throughout Durham. In most cases, projects shown are City projects, but other State projects may be listed well. This page will be updated frequently to provide the latest information available. Projects listed support Durham’s Strategic Plan goal of maintaining the city’s physical assets.

Bookmark this page to remain informed on major projects in Durham, including ongoing street repaving progress.

Projects

American Tobacco District Waterline Replacement

Study/Design Phase – East of Roxboro Street
  •  Estimated Start: Early 2016
  •  Estimated Completion: Mid-2016
Construction Phase – East of Roxboro Street
  •  Estimated Start: Mid-to-late 2016
  •  Estimated Completion: Early-to-mid 2017
Study/Design Phase – American Tobacco District
  • Estimated Start: 2016
  • Estimated Completion: Late 2016
Construction Phase – American Tobacco District
  • Estimated Start: 2017
  • Estimated Completion: 2018
For information, visit the American Tobacco District Waterline Replacement page.

Downtown Loop Water Main


For more information, please visit the Downtown Loop Water Main Replacement and Meter Upgrade page.

2-Inch Water Line Replacement Project


Design Phase
  • Estimated completion: February 2016
Construction Phase
  • Estimated start date: May 2016
For information, visit the 2-inch Water Line Replacement Project page.

Durham Central Park Project


Durham Central Park waterline replacement
  • Estimated start date: Late 2016
  • Estimated completion: Summer 2018
For information, visit the Durham Central Water Park Waterline Replacement page.